Cement · UltraTech · 50 kg bag

UltraTech PPC cement (plain bag): the everyday bag for plaster, brickwork and flooring

The short answer
  • Brickwork, inside and outside plaster Best fit
  • Floor base, footing and PCC bed Fine
  • Columns, beams, slab Fine, with 10–14 days curing
  • Open roof slab, wet-soil footing Step up a bag

PPC is Portland Pozzolana Cement: cement blended with fly ash. It has no 43 or 53 grade number. UltraTech's own page says "there are no grades in PPC" and puts its strength at 330 kg per sq cm, the same as OPC 33. It sets slower than OPC and gives off less heat, which is kind to plaster in a Bihar summer. Check the type line on the bag when it arrives: our bills show the plain bag as PPC on some deliveries and as composite on others, and both are fine for house work.

50 kg
Bag sizePlain HDPE bag, GST bill. Delivery is charged separately.
0
Grade numbersNo "43" or "53" on PPC. If a seller says 43, ask to see the bag.
33 MPa
Strength at 28 daysThe minimum IS 1489 asks. Same as OPC 33 grade.
18%
GST on the billCement GST is 18% since 22 Sep 2025.
Today's rate, per 50 kg bag, with GST billAsk rateSee cement rates →
The bag, and the four things to read on it
UltraTech PPC bag with four things to readA plain 50 kg bag. 1: the type line, PPC. 2: the standard number, IS 1489 for PPC. 3: the ISI mark and the weight, 50 kg. 4: the packing date, month and year. ULTRATECH PPC POZZOLANA CEMENT IS 1489 ISI 50 kg PACKED ON MM / YYYY 1234 1 Type linePPC = fly ash cement 2 Standard no.IS 1489 means PPC 3 ISI mark, 50 kgweight is printed 4 Packing dateuse within ~3 months Generic drawing. Layout differs by lot.
Drawn to show what to look for. Where each item is printed differs from lot to lot, so send us a photo of your bag.
What PPC means

Cement blended with fly ash, rated by days, not by a number

Brand pages say "PPC" and stop. Here is what the letters mean and what strength the standard asks for on which day.

What is inside the bag
Composition of PPCClinker and gypsum 65 to 85 percent, fly ash 15 to 35 percent. What is inside a PPC bag Clinker + gypsum 65–85% Fly ash 15–35% Fly ash works slowly and keeps adding strength later. The rest is the same clinker and gypsum as OPC. Range from IS 1489 (Part 1). Drawn at the middle.
Fly ash is a fine powder left from power stations. Because it reacts slowly, PPC is weaker in the first week and catches up later.
Strength the standard asks, by day
Minimum strength of PPC at 3, 7 and 28 daysBars at 16, 22 and 33 MPa for 3, 7 and 28 days. 33 equals OPC 33 grade. Minimum strength for PPC (MPa) 163 days227 days3328 days 33 = OPC 33 grade
Minimums from IS 1489 (Part 1), as published by JK Cement. Bags from the factory test above these numbers. UltraTech states the grade strength as 330 kg per sq cm, which is the same 33 MPa.
What UltraTech does not tell youUltraTech's PPC page gives no IS number, no bag weight, no setting time and no price. The number on a PPC bag is IS 1489. In the standard, setting starts after at least 30 minutes and ends within 10 hours; in practice PPC stays workable a little longer.
Where it goes

Which part of the house takes the plain bag

Numbers on the drawing match the table. Plaster and brickwork take a large share of a house's bags and gain nothing from a costlier bag.

One house, six places for cement
Cross-section of a house with six numbered places1 footing and plinth, 2 brickwork, 3 plaster, 4 floor base, 5 columns beams and slab, 6 top roof slab with water-repellent bag and coating. 652341 Plaster both sides Footing Plain PPCWeather PlusPremium
Grey: plain PPC is right. Blue: for the open roof we give Weather Plus. Yellow: footings in wet soil can take Premium.
Part of the housePlain PPCWhat to know
1Footing and plinthFineRCC and PCC are on UltraTech's list for PPC, and low heat suits a big pour. In wet soil, Premium is the step up.
2BrickworkBest fitMortar stays workable longer, so the mason is not fighting a stiff mix in May.
3Plaster, inside and outsideBest fitUltraTech lists plastering. Less heat means fewer hairline cracks. See cement for plaster.
4Floor baseBest fitBig area, no hurry. Keep it wet the full time before tiles go on.
5Columns, beams, slabFine, with careCure at least 10 days; 14 is better. Keep the props in longer than the OPC timetable. If the drawing names OPC or a grade, follow the drawing. Super if you want faster early strength.
6Top roof slab, open to the skyStep upPPC can be cast here, but we give Weather Plus and a roof coating. No bag replaces the coating.

All four UltraTech bags side by side, with the price gap: PPC vs Super vs Premium vs Weather Plus. OPC or PPC for the frame: OPC vs PPC.

Read the bag

Check the bag you get, before it is unloaded

The type line matters more than the name

Every cement bag prints its type and the Indian Standard it is made to. The plain UltraTech bag can come as PPC (IS 1489) on one delivery and as composite (IS 16415) on the next: our own bills list both. Both are fine for house work. Just keep one kind per pour or per wall. To check a bag is genuine, see asli ya nakli: cement.

PPCIS 1489
fly ash
CompositeIS 16415
fly ash + slag
OPCIS 269
no blend
Use it fresh
Time line from packing dateBest used within about 3 months of the packing date. Older bags should be tested before use. Best: within ~3 months Older: test first Packing date +3 months Older bag: rub a handful between your fingers. Soft powder is fine. Hard lumps are not.
Cement is best used within about 3 months of the date printed on the bag, kept dry (UltraTech's guidance). Stack bags on planks, off the floor, under cover, and use the oldest first.
Send us a photo, not a visitWhatsApp a photo of the bag front and back (the type line, the IS number and the packing date) and we will tell you what it is and whether it is fresh. Delivery and unloading are charged separately, see delivery. More on dates: how old can cement be.
Bags per trolley

How many bags go with a trolley of sand

Masons ask this every week. One bag of cement is taken as 1.25 cubic feet. Multiply by the mix and you get the sand one bag can carry.

JobMix (cement : sand)Sand per bagBags per 100 cft trolley
Floor screed under tiles1 : 33.75 cftabout 27
Outside plaster1 : 45 cft20
Brickwork and inside plaster1 : 67.5 cftabout 13

These are common site mixes, not maker figures: follow your engineer's drawing. Trolleys differ, usually between 80 and 120 cft, so ask your driver for the real size. Damp sand takes more room (bulking), so in the rains add a bag or two. Whole-house figure: cement, sand and aggregate calculator.

Mistakes we see

Four ways PPC goes wrong

Curing for 7 days, like OPC

PPC needs at least 10 days of wet curing, and 14 is better (IS 456, clause 13.5.1). In an April to June sun, count every slab as hot and dry.

Two kinds of bag in one pour

PPC, OPC and composite set at different speeds. Use one kind per pour or wall. A column on one day and a slab on another can differ.

Using a lumpy, old bag

Lumps that stay hard mean damp has got in. Keep that bag out of the slab and check the packing date on every delivery.

Taking the props out on the OPC day

The standard's prop times assume OPC. PPC starts slower, so leave the props longer and ask your engineer for the exact day.

On our shelf

Order UltraTech PPC, and what goes with it

Every product can be ordered; if a pack size is not on the shelf, we order it for you, just ask on WhatsApp how long it takes. Today's price for every bag: cement rates. Delivery and unloading are charged separately.

Questions people ask us

Short answers

Is PPC fine for a slab?

Yes. UltraTech lists RCC among the uses of PPC. It starts slower than OPC, so cure at least 10 days (14 is better), keep the props in longer than the OPC timetable, and do not stack bricks or bags on a new slab in the first week. If the drawing names OPC or a grade, follow the drawing. For an open roof, see Weather Plus.

Can PPC and OPC be mixed?

Not in the same pour, wall or batch: they set at different speeds. In different parts of the house, yes: PPC for the plaster and OPC for a precast lintel is normal. The same goes for PPC and composite bags. More in OPC vs PPC.

How do I read the date on the bag?

The bag prints its packing month and year. UltraTech's guidance is to use cement within about 3 months of that date, kept dry. Older bags are not useless, but rub a handful: soft powder is fine, hard lumps are not. Where the date sits changes from lot to lot, so send us a photo and we will point it out. More in how old can cement be.

How many bags per trolley of sand?

For a 100 cft trolley: about 27 bags for a 1:3 floor screed, 20 bags for 1:4 outside plaster and about 13 bags for 1:6 brickwork or inside plaster. Check your trolley's real size and add a bag or two when the sand is damp. See the table.

Is UltraTech PPC 43 grade or 53 grade?

Neither. UltraTech's page says "there are no grades in PPC" and gives a grade strength of 330 kg per sq cm, the same as OPC 33. Some online listings write "43 grade" or "53 grade" for PPC; that is not what UltraTech says. Read the type line and the IS number on the bag.

What is the price of UltraTech PPC today?

Today's rate for the 50 kg bag is on our cement rate page, with a GST bill (cement GST is 18%). Delivery and unloading are charged separately. Send the number of bags on WhatsApp and we will reply with the total.

Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures

Civil engineer at our Reva Road store, Muzaffarpur, advising on cement, steel and building work. Every figure on this page was checked on 12 Nov 2026 against UltraTech's own page, the Indian Standards and our own supplier bills. Where the sources are silent, the page says so.

Where the facts come from

  1. UltraTech, PPC page: fly ash blend, "no grades in PPC", grade strength 330 kg/sq cm, uses in RCC, PCC, masonry and plaster. The page gives no IS number, bag weight, setting time or price.
  2. IS 1489 (Part 1), as published in JK Cement's PPC guide: fly ash 15–35%, minimum strength 16, 22 and 33 MPa at 3, 7 and 28 days, setting not before 30 minutes and not after 10 hours.
  3. IS 456:2000, clause 13.5.1: wet curing at least 10 days for blended cements, 14 recommended; prop-removal times assume OPC. Types on the bag: IS 1489 (PPC), IS 16415 (composite), IS 269 (OPC).
  4. Shelf life of about 3 months from the packing date: UltraTech's guidance, as quoted on our OPC vs PPC page.
  5. Our UltraTech bills, 2025–26: the plain bag supplied as PPC on some deliveries and composite on others.
  6. Bags per trolley: our own sum, 1 bag = 1.25 cft; mixes are common site mixes, not a maker's figures. Cement GST 18%: rate in force since 22 Sep 2025.

Not sure what is on your bag?

Send a photo of the bag front and back. We will tell you the type and whether it is fresh, and give you today's rate.