Roofing guide · cement sheets

How many cement sheets your roof needs: count them the way they are laid

The short answer
  1. Sheets across = roof length along the eave ÷ 1.01 m, rounded up.
  2. Rows up the slope = (slope length − 0.15 m) ÷ (sheet length − 0.15 m), rounded up.Slope length = along the slope from the wall to the ridge, plus the overhang at the eave.
  3. Sheets = across × rows. Do it for each slope of the roof.

Every 1.05 m sheet hides 44 mm under its neighbour, and every row hides 150 mm under the row above it. The top row has nothing above it, so it loses nothing at its top end. That is why you subtract 0.15 m once before dividing.

1.01 m
Width each sheet addsA 1.05 m sheet after its 44 mm side lap (Everest).
150 mm
End lap, at leastMore on roofs flatter than 18° (IS 3007).
91%
Of a 3 m sheet is roof2.88 m². Everest and Charminar print the same figure.
Looking down on a laid roof
Plan view of six cement sheets laid in two rows Three sheets across and two rows up the slope. Each sheet is 1.05 m wide but adds only 1.01 m, because 44 mm sits under the next sheet. The upper row laps at least 150 mm over the lower row. The lapped strips are shaded yellow. RIDGE UP THE SLOPE side lap 44 mm end lap ≥ 150 mm top row eave row sheet 1.05 m adds 1.01 m ALONG THE EAVE Laps: you pay for them, they don't add roof. About 9% of a 3 m sheet, 11% of a 2 m sheet.
Not to scale: the laps are drawn wider than they are. Widths and laps: Everest fibre cement sheet data. The same arithmetic gives Charminar's published 91% and 87%.
What one sheet really covers

The sheet you pay for and the roof you get

These are the four lengths on our shelf, in Everest grey and Charminar white, all 1.05 m wide and 6 mm thick. A longer sheet loses a smaller share to the same 150 mm lap.

SheetRoof it coversShareWeight
2.0 mcalled 6 ft · really 6 ft 7 in1.87 m²20 sq ft89%25 kg
2.5 mcalled 8 ft · really 8 ft 2 in2.37 m²25.5 sq ft90%31 kg
3.0 mcalled 10 ft · really 9 ft 10 in2.88 m²31 sq ft91%37–38 kg
3.6 mcalled 12 ft · really 11 ft 10 in3.48 m²37.5 sq ft92%44–46 kg

How the numbers are made

Roof covered = 1.01 m × (sheet length − 0.15 m), for a sheet with a row lapping over it. Everest prints 2.88 m² and 91% for its 3 m sheet. Charminar prints 91% for 3 m and 87% for 1.5 m. Both come out of this same sum, so the two brands agree. Weight is Charminar's 12.3–12.7 kg per metre of length.

Counting in feet? Use the metres.

The trade calls our sheets 6, 8, 10 and 12 feet, but they are made in metres. A "12 ft" sheet is 3.6 m, which is 2 inches short of 12 feet. Count a slope with 12 ft and you can come up short of a row.

For the whole roof

With 3 m sheets, every 100 m² of roof takes about 109.4 m² of sheet (3.15 ÷ 2.88). Sheets in the top row cover their full length, 1.01 m × the length, so a one-row roof does a little better.

Before you count

Measure along the slope, not across the floor

Sheets run up the slope, so the length that matters is the sloping one. It is always longer than the floor plan.

End view of a two-slope roof A building 6.0 m wide with the ridge 1.5 m above the wall top. Each half has a run of 3.0 m, so the slope is 3.35 m. With a 0.25 m overhang the sheet must be 3.6 m long. Four purlins on each side, none more than 1.4 m apart. rise 1.5 m run 3.0 m building width 6.0 m slope 3.35 m 27° overhang 0.25 m purlins, at most 1.4 m apart ridge √(3.0² + 1.5²) = 3.35 m + 0.25 m overhang = 3.60 m one 3.6 m sheet per side, no end lap
Purlin limit and 0.3 m maximum overhang: Everest and IS 3007 (Part 1). This roof is worked out in Example 2 below.
  1. Eave length. Measure the roof along its lower edge, end to end, including any overhang past the end walls.
  2. Run. The flat distance from the eave wall to the point under the ridge. Half the building width for a two-slope roof, the full width for a one-slope shed.
  3. Rise. How much higher the ridge (or the high wall) is than the eave wall.
  4. Slope = √(run² + rise²). Or multiply the run by the number in the table below. If the frame is already up, simply run a tape along a rafter from the wall to the ridge purlin.
  5. Add the overhang at the eave, so rain drips clear of the wall. Keep it 0.3 m or less: a longer free edge snaps in an April storm.
Rise is aboutSlope = run ×Angle
¼ of the run1.0314°: too flat, end laps must grow
⅓ of the run1.0518°: the least IS 3007 prefers
⅖ of the run1.0822°
½ of the run1.1227°

Below 18°, IS 3007 asks for end laps longer than 150 mm and the joints sealed as the maker advises. That changes the count, so talk to us first. How to lay the sheets once they arrive: laying cement sheets.

Two roofs, worked out

A shed and a house roof, step by step

Both are sizes we are asked about every week. Follow the same steps with your own numbers, or let the counter below do it.

Side view of a one-slope shed with two rows of 2.5 m sheets 2.5 m 2.5 m end lap 150 mm overhang 0.2 m run 4.4 m rise 1.5 m 5 purlins, none more than 1.4 m apart

Example 1: a one-slope shed

Cattle shed or store, 6.0 m long. Walls 4.4 m apart, the back wall 1.5 m higher than the front.
  • Slope√(4.4² + 1.5²) = 4.65 m, about 19°. Add a 0.2 m overhang: 4.85 m.
  • Across6.0 ÷ 1.01 = 5.94, so 6 sheets.
  • RowsWith 2.5 m sheets: (4.85 − 0.15) ÷ (2.5 − 0.15) = 4.70 ÷ 2.35 = 2 rows.
  • Bolts5 purlins × 6 sheets × 2 = 60, with 60 washer sets.
12 sheets of 2.5 m (8 ft), about 375 kg to carry.With 3 m sheets it is also 2 rows, but 12 × 3 m buys 6 m more sheet that ends up as extra lap or gets cut off. The shorter sheet is the right buy here.
Plan of a two-slope roof, 8 sheets each side eave · 8.0 m ÷ 1.01 = 8 sheets 8 × 3.6 m 8 × 3.6 m ridge: 8 pairs, fixed with the top bolts

Example 2: a house roof with two slopes

Building 8.0 m long and 6.0 m wide, ridge 1.5 m above the wall top: the roof drawn above.
  • SlopeRun 3.0 m, so √(3.0² + 1.5²) = 3.35 m. Add 0.25 m overhang: 3.60 m.
  • RowsOne 3.6 m sheet reaches eave to ridge: 1 row, no end lap at all.
  • Across8.0 ÷ 1.01 = 7.92, so 8 per side.
  • Bolts4 purlins × 8 sheets × 2 × 2 sides = 128, with 128 washer sets.
16 sheets of 3.6 m (12 ft) and 8 ridge pairs, about 720 kg.One sheet from eave to ridge means no end lap, and the end lap is where wind-blown rain gets in. If a single length can reach, take it.
Count your roof

Sheets, ridges and bolts for your roof

Put in your roof size. The counter tries every mix of our four lengths and picks the one that buys the least sheet, then counts the bolts the way IS 3007 does.

End to end, including any overhang past the end walls.
—

Your list

—
Material totalAsk rate
Send this list on WhatsApp

Prices are filled in from today's sheet rate. Cutting and delivery are charged separately; ask for the amount for your site (delivery). Hip roofs, L-shaped roofs and roofs with a valley: send us the drawing. More options: roofing sheet calculator.

Not only sheets

Ridges, bolts and washers: count them with the sheets

A sheet roof leaks at its fixings far more often than through a sheet. Buy them in the same trip so the mistri is not tempted to make do.

J-bolt fixing a cement sheet to an angle purlin Cross-section of the corrugated sheet. The J-bolt goes through a hole drilled in the crown of the wave, with a bitumen or EPDM washer and a galvanized iron washer under the nut, and hooks under the angle purlin. Water runs in the valley, which is never drilled. nut, hand-tight GI washer bitumen or EPDM washer Drill here: the crown of the wave valley: water runs here, never drill angle purlin J-bolt, 8 mm or more bolt length = purlin depth + 75 mm (+ 90 mm at laps and the ridge)
Fixing details from IS 3007 (Part 1) and Everest's laying instructions. Not to scale.

What to buy with the sheets

  • J-bolts or L-bolts: 2 for every sheet at every purlin it rests on. That is IS 3007's count, so a slope needs 2 × sheets across × purlins. J-bolts for angle-iron and pipe purlins, L-bolts (hook bolts) for joists, concrete or wooden purlins.
  • Washers: one set per bolt, a bitumen washer under a galvanized iron one, or an EPDM washer as Everest and Charminar supply. Charminar says a squeezed EPDM washer must never be reused.
  • Ridge pieces on a two-slope roof: one pair for each sheet across. They go on with the same bolts as the top row of sheets, so they need longer bolts, not more bolts.
  • Bolt length: purlin depth + 75 mm, or + 90 mm where two sheets overlap or a ridge sits on top. Tell us your purlin size (for example a 50 mm angle) and we give the right length.
  • Spare sheets: usual practice is one or two for breakage in loading and drilling. Not 10%: the count is already rounded up.
IS 3007 allows one bolt per sheet at middle purlins in calm places. North Bihar's April–May aandhi is not calm, so we count two everywhere. More: keeping sheets on in a storm.
Ridges, J-bolts, L-bolts and washers: we can order them for you with the sheets; ask on WhatsApp for the time it takes. Ridges, bolts and washers.
Where counts go wrong

Six ways to buy the wrong number of sheets

Each one we have seen at the counter. Most leave you short, which means a second trip with half the roof open.

29.1 m² ÷ 2.88 = 11 sheets? roof 6.0 × 4.85 m needs 6 × 2 = 12

Dividing the roof area by 2.88

You get: one sheet short

Sheets come in whole rows and whole columns, so round each one up first, then multiply. The area shortcut most online calculators use rounds only once.

floor 4.4 m slope 4.65 m gap

Measuring the floor, not the slope

You get: sheets that stop short of the ridge

The slope is always longer than the plan: 4.65 m against 4.4 m here, before the overhang. Use √(run² + rise²).

12 ft sheet 3.6 m 6 cm short on every sheet

Counting with "12 ft" for a 3.6 m sheet

You get: a slope that misses by a few inches

Our "10 ft" and "12 ft" sheets are 3.0 m and 3.6 m. On a slope that only just fits, those inches decide whether one row is enough.

0.44 m > 0.3 m

A sheet too long, left as overhang

You get: an edge that cracks in the first storm

IS 3007 and Everest cap the free overhang at 0.3 m. If your sheet is longer than the slope needs, cut it with a saw or choose the shorter length.

3rd row: not needed 4.85 ÷ 2.35 = 2.06 → 3 rows? 4.70 ÷ 2.35 = 2.0 → 2 rows

Taking a lap off the top row too

You get: a row of sheets you didn't need

Slope ÷ (length − 0.15) charges the top row a lap it doesn't have. Subtract 0.15 m from the slope first. In Example 1 the short rule says 18 sheets; the right count is 12.

hole in the valley

Bolts in the valley, washers forgotten

You get: drips at every bolt

Water runs in the valley. Bolts go through the crown, drilled (never punched), at least 75 mm from any edge, each with its washers, tightened only until the washer seats.

Questions people ask us

Short answers

How do I calculate how many roofing sheets I need? (kitni chadar lagegi)

Sheets across = roof length along the eave ÷ 1.01 m, rounded up. Rows = (slope length − 0.15 m) ÷ (sheet length − 0.15 m), rounded up, where the slope length runs along the slope from the wall to the ridge, plus the overhang. Multiply, and do it for each slope. Or use the counter above.

How much area does one 3 m (10 ft) sheet cover?

2.88 m², about 31 sq ft, once it is lapped on its side and at one end. That is 91% of the sheet, the figure both Everest and Charminar publish. A sheet in the top row, with nothing over it, covers its full length: 3.03 m².

How much should the sheets overlap?

Everest gives a side lap of 44 mm, which is why its 1.05 m sheet covers 1.01 m, and an end lap of at least 150 mm. The Indian code, IS 3007, describes the side lap as half a corrugation and asks for longer end laps on roofs flatter than 18°. For these sheets we go by the maker's 1.01 m.

Which sheet length should I buy?

If one length reaches from the eave to the ridge with an overhang of 0.3 m or less, take it: no end lap, so nowhere for blown rain to get in. If not, the mix that buys the least sheet, which is often not the longest. The counter tries every mix of our four lengths.

How many J-bolts per sheet?

Two at every purlin the sheet rests on. A 3 m sheet usually sits on three purlins, so six bolts, some shared with the row above. For a whole slope: 2 × sheets across × purlins, one washer set per bolt.

Do I measure the floor or the slope?

The slope. A roof that spans 3.0 m on plan with the ridge 1.5 m higher is 3.35 m along the slope, before the overhang.

How many extra sheets should I order?

The count already rounds up, so no 10% on top. Usual practice is one or two spares for breakage in loading and drilling.

What is the price of a 10 ft or 12 ft cement sheet?

It changes with the market, so it is on our sheet rate page for each length and brand, updated on the day shown.

Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures

Cement, steel and roofing at our Reva Road store, Muzaffarpur. Every figure on this page was checked on 12 Nov 2026 against Everest's and Charminar's own product pages and IS 3007, the Indian code for laying these sheets. Where they differ, the page says so and uses the safer figure.

Where the numbers come from

  1. Everest Industries, Fibre Cement Roofing: lengths, overall width 1.05 m, cover width 1.01 m, 2.88 m² and 91% for a 3 m sheet, purlins at most 1.4 m, overhang at most 0.3 m, end lap at least 150 mm, side lap 44 mm. (The same page prints 10.77 m² of sheet per 10 m² of roof, which does not match its own 2.88 m²; the sum gives 10.94, so we use that.)
  2. Everest, fibre cement sheet brochure (Hindi): bolts through the crown, drill not punch, EPDM washers, tighten by hand and evenly after a run of sheets, mitred corners.
  3. Everest, Hi-Tech brochure: a different, wider profile (1,097 mm, 1,047 mm laid). Its figures do not apply to the 1.05 m sheets on this page.
  4. BirlaNu, Charminar Fiber Cement Roofs: 1,050 mm wide, 6 mm, IS 459, about 12.3–12.7 kg per metre, effective coverage 91% (3 m) and 87% (1.5 m).
  5. BirlaNu, Charminar Tools & Accessories: J-bolts, L-bolts, 22 mm EPDM washers; EPDM washers are not to be reused.
  6. Bureau of Indian Standards, IS 3007 (Part 1):1999, laying of corrugated sheets: pitch preferably 18° or more, end lap at least 150 mm, overhang at most 300 mm, purlins at most 1.4 m for 6 mm sheets, ridge purlin 75–115 mm from the apex, Table 2 bolt count, bolt lengths and washers, shorter courses at the eaves.