Check list · for the owner

How to check the painter's work at each step, before you pay

The short answer

Come and look six times, not once at the end. A bad finish is almost always made in a layer you can no longer see. Check the putty before the primer covers it, the primer before the paint covers it, and count the tins after each coat. Then do one slow walk-round, collect the papers, and pay.

½
Of the paint, after coat 1Opus prints coverage for 2 coats, so one coat uses about half.
≤ 1.5 mm
Both putty coats togetherBirla White's limit. A thick crust at the switchboard is a warning.
15 days
To register the warrantyFrom the purchase date, with the GST bill (Birla Opus).
Six times to stop and look
The six checks during a paint job A strip of six wall samples, one per stage. 1, putty after sanding: hold a torch flat on the wall. 2, primer: rub a dry palm, no white dust. 3, first coat: about half the paint used, some patchiness is normal. 4, second coat: even colour, no white showing. 5, final look a day or two later: edges, switchboards, grills, floor. 6, tins and papers: count the empty tins, keep the bill and register the warranty. 1 2 3 4 5 6 Putty, after sanding Primer over putty Paint, coat 1 Paint, coat 2 Final look Tins and papers torch flat on the wall:no ridges, no pits dry palm on the wall:no white dust about half the paint used;light patches are normal even colour, no whiteshowing through a day or two later: edges,boards, grills, floor count empties; bill, card,registration done pay the last part after stop 6
Stops 1 and 2 matter most: once the next layer is on, a fault there can only be fixed by scraping back.
The six stops

What to look at, and when to come

Tell the painter on day one that you will look at the wall at these six points and that he should call you before covering a layer. A good painter is glad of it. The order of layers and the waiting times are on putty, primer, paint; this page is only about checking them.

0

Before the first brush

Come on the first morning
Look at
The tins. Sealed lids, the product name you were quoted (not just "Birla Opus" or "emulsion"), the shade code written on each tinted tin, and the QR code Birla Opus prints on its cans. Keep the GST bill: every tin should be on it.
And the wall
Dry to the touch and even in colour. New plaster needs 28 days of curing (Opus sheets). Any wet patch or seelan stops the job here: painting a damp wall.

Open the tins in front of me, please, and keep the empty ones for me to count.

1

Putty, after sanding

Before the primer goes on over it
Look at
Hold a torch flat against the wall and shine it along the surface. Ridges, trowel lines and pits throw shadows. Check corners and around switchboards, where putty piles up.
Wrong if
A thick white crust: Birla White caps both coats at 1.5 mm and says WallCare is not for filling dips. Dips belong in the plaster. Dust left on the wall: wipe a palm across it.

Please sand this patch again with fine paper and wipe the dust off before the primer.

2

Primer over the putty

Before the first coat of paint
Look at
The whole wall should be one even, slightly off-white, with no bare white strips at the edges or behind doors. Rub a dry palm firmly: bare putty leaves white powder, primed putty does not.
Wrong if
No primer tin opened, or one tin for a whole floor. Primer is thinned 1 L to 1 L of water, not more (Opus sheets). Paint straight on putty comes out patchy. Which primer goes where: primers.

Show me the primer tin before you start the paint.

3

Paint, coat 1

When he says the first coat is done
Look at
Count the tins. Birla Opus prints coverage for two coats, so the first coat should use about half the paint the job needs. Use the tin check below.
Normal
Some light patches and white showing faintly. That is what the second coat is for. Do not judge the colour yet.
Wrong if
Paint looks watery and runs. Style Color Smart takes 500–600 ml of water per litre of paint, not more (Opus sheet).

Call me when coat one is finished on each room, before you start coat two.

4

Paint, coat 2

At least 4–6 hours after coat 1
Look at
One even colour from every angle, no white showing through, no roller lines. Nearly all the planned paint should now be used.
Wrong if
Patches remain. The Opus sheets allow a third coat; outside walls take 2–3 coats, with an extra one on parapet tops and chhajjas. If coat 2 went on within an hour of coat 1, it was on a wet coat.

This wall still shows white near the window. Please give it one more coat.

5

Final look

A day or two after the last coat (usual practice)
Look at
Daylight first, then a torch flat along each wall. Run a hand for grit, roller fluff and dried drips. Then the edges, boards, grills and floor on the walk-round list.
Don't
Wipe with a wet cloth to test it. The Opus interior sheets ask for two weeks before wet cleaning.

Let's walk the house together with this list and mark the spots with tape.

Stop 6, the tins and the papers, is below: litres used vs bought and warranty papers.

No tools needed

Three tests anyone can do

You don't need to know painting. A phone torch, your palm and a count of tins catch most short-cuts. These are usual site practice, not maker tests.

The torch test Top: a wall lit from the front looks smooth. Bottom: the same wall with a phone torch held flat against it, shining along the surface. Ridges and pits now throw shadows and can be seen. LIGHT FROM THE FRONT looks smooth TORCH FLAT ALONG THE WALL ridges, roller lines and pits show up
Do it at night or with the curtains shut. Hold the phone against the wall, light pointing along it, and walk it slowly across.

1The torch

Light from the front hides faults; light skimming along the wall shows them. Use it on the putty (stop 1) and the final coat (stop 5). Painters call this a side-light check. A few faint marks are normal on hand work; lines you can feel with a fingertip are not.

2The palm

A dry palm pressed and drawn across the wall tells you three things. White powder before primer: dust left after sanding. White powder after primer: the primer was skipped or too thin. Gritty feel on the finish: dust or sand under the paint.

3The tins

Paint does not disappear. Tins bought, minus tins left, is what went on the wall, and the coverage on the tin says what two coats need. Far less used means a coat or the primer is short, or too much water. Work it out in the tin check.

If something looks wrong on a damp ground-floor wall, it may not be the painter: bubbles and white salt usually come from water in the wall. See why paint peels before you blame the work.

Stop 6, part one

Litres used against litres bought

Put in the area painted, the paint, and the litres bought and left over. Count litres from the tins, before water: the makers' coverage is per litre in the tin. If you don't know the area, get it from litres per room.

571 sq ft = one 12×12 ft room, 10 ft high, ceiling included, one door and two windows off. Whole house: inside ≈ 3.5 × carpet area, outside ≈ 1.5 × (Birla Opus).
Open tins: guess by eye. A tin a quarter full counts as a quarter of its size.

What your walls took

Paint used—Bought less what is left over
Expected for 2 coats——
—
Primer on new inside walls, 2 coats—ActivCoat Interior: 110–140 sq ft/L on plaster, 170–200 on putty, per coat (Birla White)
Putty on new inside walls, 2 coats—WallCare: 17–20 sq ft per kg for 2 coats (Birla White)
Ask us to check these figures

Expected range from the paint's own sheet (sq ft per litre for 2 coats). Our flags: below 85% of the low figure, or above 125% of the high figure (Opus allows 10–20% less coverage on rough walls). A flag is a reason to ask, not proof.

Stop 5, the walk-round

Where painters cut corners, room by room

Walk each room with the painter. Tick as you go, and mark each fault with a small piece of masking tape so nothing is forgotten. This page prints as a list.

One wall, six places to look
Where to look on a painted wall A painted wall with a door on the left, a switchboard in the middle and a window with an iron grill on the right. Six numbered markers: 1 the line where the wall meets the ceiling, 2 around the switchboard, 3 the grill on all four sides, 4 enamel runs on the door frame, 5 splashes on the floor and skirting, 6 the corner and behind the door. 1 2 3 4 5 6
Wavy ceiling line (1), paint on the switchboard (2), grill bars painted only on the front (3), runs on the door frame (4), splashes (5) and a thin corner (6): the six places most faults hide.
Holding back payment, politely Usual practice, and fair to both sides:
  1. Agree before work starts that the last payment is made after a joint walk-round.
  2. Walk together, tape each spot, and give him the list on WhatsApp so there is no argument later.
  3. Give him a day for the touch-ups, check only the taped spots, and pay the same day.
Comparing rates or quotes is a separate job: painting cost per sq ft.
Stop 6, part two

The papers to hold before you pay

A warranty claim fails on missing paper far more often than on paint. Collect these three before the last payment.

The GST bill

From the store, at the time of purchase
Every tin
  • Product name, pack size and quantity of each tin, primer and putty included.
  • Both warranty clocks below start from this date.
  • Extra tins bought later: ask for them on a bill too.

Product warranty

You register it; any painter can do the job
15 days
  • Register within 15 days of purchase, on birlaopus.com or 1800 120 1234.
  • Years differ by paint, as per Birla Opus warranty card: Calista Ever Wash Shine 6, Calista Neo Star 7, One True Look 9, One True Life 12.
  • Covers manufacturing defects, when the product sheet's system was followed. Steps: registering the warranty.

Opus Assurance, 1-year repaint

Only if agreed before painting started
30 / 120 days
  • An Opus-certified painter registers the site in the Opus ID app within 30 days of your first purchase and scans every can.
  • He closes the job within 120 days; ask him to show the closed job and give you the certificate.
  • At least 2,000 sq ft of paintable area. Full terms: Opus Assurance.
Cans that were not scanned are not covered. Check the count in the app against your tin count.
Questions people ask us

Short answers

How do I know the painter really did two coats? (do coat lagaya ya nahi)

Count the paint. The coverage printed on Birla Opus tins is for both coats, so after the first coat about half the paint for the job should be used, and after the second coat nearly all of it. If two coats are claimed and only half the tins are empty, a coat is missing or the paint was thinned too much. Also ask the painter to call you when each coat is finished, and look at the wall then.

How can I tell if primer was put over the putty?

Rub a dry palm firmly on the wall before the paint goes on. Bare sanded putty leaves white powder on the hand; a primed wall feels sealed and leaves little or nothing. Also ask to see the primer tin opened. The Birla Opus interior sheets put a primer coat over the putty, thinned 1 litre primer to 1 litre water.

How much water can the painter mix in the paint?

Only what the tin's sheet says. For Style Color Smart it is 500 to 600 ml of water in 1 litre of paint; for Calista Neo Star at most 400 ml per litre for the top coats. More water spreads the paint further but hides less, and you see the putty through it.

When should I do the final check?

Once the last coat is fully dry, usually after a day or two. Check in daylight and again with a torch held flat along the wall. Do not wipe the wall with a wet cloth for two weeks, as the Birla Opus interior sheets say.

The painter used more paint than the calculator says. Is he wasting it?

Not always. Bare or rough plaster takes 10 to 20% more (Birla Opus), a deep shade or a third coat takes more, and a little is lost in the tray and roller. Far more than that, and no third coat, is worth a polite question about where the rest went.

Who registers the paint warranty?

For the Birla Opus product warranty, register within 15 days of purchase on birlaopus.com or 1800 120 1234, with the GST bill. For the one-year free repaint (Opus Assurance), an Opus-certified painter registers the site in the Opus ID app within 30 days of the first purchase and scans every can; ask him to show it.

Is it rude to keep back money until touch-ups are done?

No, it is usual practice. Agree before work starts that the last payment is made after a joint walk-round and the touch-ups on that list. Walk the house together, mark each spot, give the painter time to fix them, and pay on the same day the list is done.

I am not in Muzaffarpur while the house is painted. What can I do?

Ask someone at home to send you a short video at each stop: the torch along the putty, the primer tin opened, the empty tins after each coat. Send the videos to us on WhatsApp and we will look at them with you. Finding a painter in the first place: how to choose a painter.

Mr Mustafaa
Paint Engineer, Tashya Ventures

Paint Engineer at our Reva Road store, Muzaffarpur. The figures on this page were checked against the Birla Opus and Birla White product sheets and the Opus warranty terms on 13 Nov 2026. The torch, palm and tape checks are usual site practice and are marked as such.

Where the numbers come from

  1. Birla Opus, Style Color Smart product information sheet: 120–140 sq ft/L for 2 coats, 1 L paint + 500–600 ml water, primer 1:1, 4–6 h between coats, 28-day plaster cure, 2 weeks before wet cleaning.
  2. Birla Opus, Calista Ever Wash Shine information sheet: 130–150 sq ft/L for 2 coats.
  3. Birla Opus, Style Power Bright and Calista Neo Star sheets: 50–60 sq ft/L for 2 coats, 2–3 coats, extra coat on horizontal surfaces, Neo Star top coat at most 400 ml water per litre, no rain within 4 days.
  4. Birla Opus, paint coverage guide and Opus Assurance page: 10–20% less coverage on rough walls; paintable area ≈ 3.5 × carpet area inside, 1.5 × outside.
  5. Birla Opus, Birla Opus Assurance terms: certified contractor, registration within 30 days of first purchase, closure within 120 days, scanned cans only, 2,000 sq ft.
  6. Birla Opus warranty documents and warranty registration: register within 15 days of purchase, 1800 120 1234; years as per Birla Opus warranty card.
  7. Birla Opus Calista Sparkle Gloss enamel information sheet (W_SGE_302025_v.2): 18–24 h between enamel coats.
  8. Birla White, Wall putty work: step-by-step and WallCare putty page: 1.5 mm for both coats, not a levelling material, 17–20 sq ft/kg.
  9. Birla White, ActivCoat Interior primer page: 110–140 sq ft/L/coat on plaster, 170–200 on putty.

Not sure about a wall?

Send a photo or a short torch video on WhatsApp, with your tin count, and we will look at it with you.