Naksha pass in Muzaffarpur: who approves your plot, the papers, the fee and the 60 days

The short answer
  1. 1Find your office
  2. 2Empanelled architect draws and signs
  3. 3File with papers and fee
  4. 4Answer any objection
  5. 5Sanction, then foundation

Inside Muzaffarpur Nagar Nigam's 49 wards, the Nagar Nigam passes the naksha. In the 216 planning-area villages of six blocks, the planning authority does. Other towns of the district have their own Nagar Parishad or Nagar Panchayat. Never start the foundation on the strength of an uploaded application.

60 days
Time the rules allowFrom the date of application, under the Bihar bye-laws 2014.
₹10/m²
Nagar Nigam feeFor a house up to 10 m high, on built-up area. Village in the planning area: ₹3.
3 years
The sanction stays validThen revalidate once for 2 more years. Finish inside that.
Who passes the naksha for your plot
Approving offices in Muzaffarpur district A sketch, not a map. At the centre, Muzaffarpur Nagar Nigam with 49 wards. Around it, the planning area of 216 villages in Mushahari, Kanti, Kurhani, Marwan, Bochaha and Minapur blocks, approved by the planning authority. Part of it, villages in Kurhani, Marwan, Kanti and Mushahari, is the proposed township area where construction is stopped until 30 June 2027. Outside, the rest of the district: towns with a Nagar Parishad or Nagar Panchayat approve their own plans; ordinary villages are not under the urban bye-laws. NAGAR NIGAM 49 wards Minapur Bochaha Mushahari Kanti Kurhani Marwan Who approves Nagar Nigam · online, no cash Planning area, 216 villages · planning authority Township area · no building till 30 Jun 2027 Other towns · their Nagar Parishad / Panchayat Plain grey: ordinary villages, not under urban bye-laws
A sketch, not a map: block names show roughly where the planning area runs. The township patch is drawn from the villages named in news reports (Kurhani, Marwan, Kanti, Mushahari); confirm your khesra at the office.
Step 1

Find out which office your plot belongs to

Filing with the wrong office is the most common way to lose a month. The line between the Nagar Nigam and the planning area runs through villages, not along a main road.

ANagar Nigam wards

Muzaffarpur Nagar Nigam

All 49 wards of the city. Applications have been taken online here for some time, with no cash at the counter. The town-planning section, with assistant engineers and town planners given wards, scrutinises the drawing.

BPlanning-area villages

Planning authority

216 villages in Mushahari, Kanti, Kurhani, Marwan, Bochaha and Minapur blocks, next to the city. The same online system was extended to them. The fee table has its own, lower column for a gram panchayat inside a planning area.

CThe rest of the district

Town office, or no urban permit

A plot inside another town goes to that town's Nagar Parishad or Nagar Panchayat. An ordinary village outside the planning area is not covered by the urban bye-laws today. The Panchayati Raj Department was drafting rules in Aug 2026 for multi-storey buildings in villages near cities.

Not sure which side you are? Take the khata and khesra numbers and the mauza name (from your deed or the rasid) to the Nagar Nigam town-planning counter. They tell you the office in a minute. Village plot: read do I need a naksha pass in a village.

Check the township stop first. The Bihar Cabinet stopped sale, purchase and construction in the proposed Muzaffarpur township area until 30 June 2027 or until its master plan is final, whichever comes first. Villages named in reports are in Kurhani, Marwan, Kanti and Mushahari, near the airport and the new bypass. No naksha will pass there until then: which land is affected.

Step 2

The papers the office asks for

This is the list in the Bihar government's own guidebook for building plan approval. Your architect prepares the forms and drawings; the ownership papers come from you.

PaperWhat it provesWhere it comes from
Application, Form IIYour request for permissionArchitect fills it
Sale deed (kewala)You own the plotYour registry papers
Jamabandi or latest rasidThe land record is in your nameCircle (anchal) office, Bihar Bhumi online
LPCYou hold the land nowCircle office
Affidavit of peaceful possessionNo dispute on the plotNotary
Drawings, 4 setsplus PDF and CAD filesSite plan, floor plans, section, elevationEmpanelled architect or engineer
Supervision certificate, Form VA technical person will watch the workArchitect or engineer
Structural stability, Form IVThe frame is designed safeEngineer
Checklist, Form VINothing is missingArchitect
Fire / airport NOCOnly where the rules askNot needed for most single houses
One plot, one size, on every paper
The plot size must agree on the deed, the rasid and the drawing Three sheets: the sale deed says 2 katha, the rent receipt says 2 katha, the drawing says plot area 2,722 sq ft or 252.9 square metres. A bar below says same plot, same size, so the office does not raise a query. SALE DEED area 2 katha RASID / LPC khesra · rakba 2 katha DRAWING plot area 2,722 sq ft = 252.9 m² Same plot, same size: no query Example at 1 katha = 1,361.25 sq ft. Use your deed's figure.
Katha is not the same size everywhere in Bihar. Convert with the figure your deed or circle office uses: katha, dhur, dismil to sq ft.
Step 3

The drawing: who signs it and what the office checks

The guidebook says to hire only an architect or structural engineer empanelled by the Urban Development and Housing Department through the urban bodies. Their names and registration numbers go on every sheet.

What the office checks first

Under the Bihar Building Bye-laws 2014 and amendments
  • Open space left at the front, back and sides (setbacks), for your road width and plot size: setback rules
  • Height and number of floors, and how much of the plot is covered
  • Plinth height. The 2026 draft gives 0.45 m to 0.9 m: plinth in a flood area
  • Room, stair and kitchen sizes, parking where it applies
The setback relief notified in May 2026 (no side gap on plots up to 10 m wide) was reported for commercial buildings. For a house, go by what your architect reads in the current rules.

Who may sign

Architect or engineer, empanelled
  • Empanelled architects and engineers are listed on the urban body's or the department's website.
  • The 2026 draft defines an empanelled architect as one registered with the Council of Architecture and empanelled with UD&HD.
  • A draftsman's or mason's sketch is not accepted, however neat.
Ask the architect for his empanelment number before he starts drawing.

Get the drawing made through us

Ar. Sumit Kumar, Doric Nirmaan, with Tashya

We work with Ar. Sumit Kumar for house design: floor plan, elevation, structure, electrical and plumbing sheets. Say in your first message that you need drawings for naksha pass, so the plan is made to the bye-laws from the first sketch and not fixed after a query.

House design service · About Ar. Sumit Kumar

Talk to the architect
Steps 4 and 5

60 days by the rules, and what an objection does to the clock

These are the service timelines the Bihar government notified under the 2014 bye-laws. The office does not inspect the site before approving a house plan; the drawing and papers decide it.

Naksha pass timeline Day 0: file the application. The office scrutinises it. By day 60: sanction letter in Form VIII-A, or refusal in Form IX. If the office raises an objection instead, you have 30 days to correct and resubmit, and the office decides within 30 days of the resubmission. After the sanction: start the foundation. The sanction is valid for 3 years and can be revalidated once for 2 years. After the work: notice of completion and occupancy certificate, fee Rs 1,000, within 30 days. APPROVALAFTER THE SANCTION Day 0 · file online papers + drawings + fee office scrutiny no site visit By day 60 · sanction Form VIII-A (refusal: Form IX) IF OBJECTION 30 days you correct and resubmit 30 days office decides miss it: plan rejected Foundation only after the sanction letter How long the sanction lasts 3 years valid +2 if revalidated Revalidate before the 3 years end. Not done in 5: apply afresh. ✓ House finished notice of completion + 3 sets of as-built plans Occupancy certificate fee ₹1,000 · site inspection · 30 days Source: UD&HD guidebook, Bihar Building Bye-laws 2014.
StageTimeWhat you do
FileDay 0Architect uploads; you pay the fee. Keep the application number.
Scrutiny≤ 60 daysWatch the status. Pick up the phone when the office calls.
Objectionif raised30 + 30Correct and resubmit within 30 days. The office then decides within 30. A second chance is given once; after that it is rejected.
SanctionForm VIII-APrint it. Keep a copy on site with the stamped drawing.
Build3 + 2 yrsBuild as drawn. A new floor later needs a revised plan first.
Occupancy30 daysApply after completion, ₹1,000. Banks and buyers ask for it.
Which portal?Nagar Nigam applications have run online for some time. On 1 Nov 2026 Bihar launched its UPYOG portal for all 264 urban bodies, with building plan approval among its services; the national tracker still showed Bihar as being set up. Ask the town-planning counter which portal is taking applications the week you file. Your architect normally holds the login and uploads for you.
What slows it downNot the office's 60 days, but papers that disagree with each other and drawings that break a setback. One complete file beats two quick ones.
The government fee

The fee is charged per square metre of built-up area

This is the residential table in the Bihar UD&HD guidebook, in rupees per sq m of built-up area on all floors. Muzaffarpur's population is under 10 lakh (Census 2011), so the Nagar Nigam column is the "up to 10 lakh" one. The portal shows the final amount on the day.

Building heightPlanning-area villageNagar PanchayatNagar ParishadNagar Nigam
Up to 10 musually up to ground + 2₹3₹4₹6₹10
10 to 15 m₹5₹6₹8₹15
Above 15 m₹6₹8₹12₹20

Non-residential buildings pay double. If the ground floor is a shop, ask the office how it counts that floor. The architect's drawing fee, notary and copies are separate; ask him for his fee first: house design.

Built-up area: 2,000 sq ft = 186 m²

Fee by the guidebook table

Building permit fee₹1,858₹10 per m², Nagar Nigam, up to 10 m
Under the 2026 draftLow riskPlot up to 300 m² and height up to 10 m
Send this to us for drawings

Rates from the UD&HD guidebook under the 2014 bye-laws. Other charges the portal adds, and any later revision, are not included. 1 m² = 10.764 sq ft.

Coming, not yet law

The 2026 draft bye-laws would make most houses "low risk"

The Urban Development and Housing Department has put out a draft of new Bihar Building Byelaws 2026. On 13 Nov 2026 it was still a draft. Until it is notified, the 2014 rules and the 60 days above apply.

ResidentialLow riskModerateHigh
HeightUp to 10 m (G+2)10–15 mAbove 15 m
Plot areaUp to 300 m²about 3,229 sq ft300–500 m²Above 500 m²
RouteEmpanelled third-party architect submits plans, affidavit and site report; permit deemed granted, work can startSame, plus a certificate that the plan meets disaster-safety guidelinesObjections in one go within 15 days; decision within 30 days
Valid for5 years, plus 2 on revalidation

A building that falls in two classes counts in the higher one. More than 8 flats is always high risk. If a permit is got by false papers, it can be withdrawn.

What it means for a Muzaffarpur family

  • A 1 to 2 katha plot (about 126 to 253 m²) with ground + 1 or ground + 2 would be low risk.
  • The architect carries more responsibility: he certifies the drawing and the site. Pick one who will stand behind his signature.
  • Deviation from the submitted plan can be acted on. Build exactly what was filed.
  • When it is notified, we will update this page. Until then, file under the current rules.
What goes wrong

Four mistakes we hear about at the counter

Filed at the wrong office

Weeks go before anyone opens it

Plots on the city's edge are the usual case. Ask with your khesra number before the architect uploads.

Sizes that do not match

Objection, 30 days lost

Deed in katha, drawing in sq ft from a tape that measured differently. Settle the figure first: katha to sq ft.

Foundation on the day of upload

Building without a sanction

An application number is not a permit. If the plan then changes on objection, the footing may be in the wrong place.

Building more than was passed

Trouble with loans, sale and the occupancy certificate

Planning a floor later? Get the column and footing sizes drawn for it now, and file a revised plan before you build it.

Once the sanction is in your hand

Buy for the drawing that was passed

Order the foundation material from the sanctioned drawing and its structure sheet, not from the first sketch. Send us the sheets and we price every item at today's rate. Anything not on our shelf we can order for you; ask on WhatsApp for the time it takes.

Cutting and delivery are charged separately; ask for the amount for your site: delivery. Rough total for your house: house construction cost calculator · today's prices: cement · sariya.

Questions people ask us

Short answers

How do I get a naksha passed in Muzaffarpur? (naksha pass kaise karaye)

Find the office for your plot (Nagar Nigam, planning authority, or the town's Nagar Parishad or Nagar Panchayat). Get the drawing made and signed by an empanelled architect or engineer, file it with the ownership papers and fee, answer any objection within 30 days, and start the foundation only after the sanction letter.

Is naksha pass online in Muzaffarpur?

Yes. Nagar Nigam applications have been online for some time, and the planning-area villages were added later. Bihar's UPYOG portal, launched on 1 Nov 2026 for all 264 urban bodies, lists building plan approval among its services. Ask the town-planning counter which portal is live when you file; the architect usually uploads.

What documents are needed for naksha pass?

Form II, 4 sets of drawings with PDF and CAD files, sale deed, jamabandi or rasid, LPC, an affidavit of peaceful possession, Form V (supervision), Form IV (structural stability), Form VI (checklist) and the fee. Fire and airport NOCs only where they apply.

How long does naksha pass take?

60 days from the application under the 2014 rules. An objection gives you 30 days to resubmit, and the office decides within 30 days after that.

What is the naksha pass fee?

By the guidebook table, ₹10 per sq m of built-up area in the Nagar Nigam for a house up to 10 m high, ₹3 in a planning-area village. A 1,000 sq ft ground plus 1,000 sq ft first floor is about 186 m², so about ₹1,858 in the Nagar Nigam. The portal shows the final figure. More: naksha pass fees.

Do I need a naksha pass for a house in a village?

Yes in the 216 planning-area villages and inside any Nagar Parishad or Nagar Panchayat. Ordinary villages outside these are not under the urban bye-laws today. See village naksha pass.

Who can sign my naksha drawing?

An architect or engineer empanelled with the Urban Development and Housing Department through the urban bodies; the list is on their websites. We can put you in touch with Ar. Sumit Kumar of Doric Nirmaan: about him.

I want to add a floor later. Does the first sanction cover it?

No. The sanction covers what was drawn. File a revised plan before building the new floor, and have the footing and columns designed for it from the start, so the revision is only paperwork.

Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures

Answers cement, steel and building questions at our Reva Road store, Muzaffarpur. The steps, timelines and fees on this page are from the Bihar Urban Development and Housing Department's guidebook and the 2026 draft bye-laws, read on 13 Nov 2026. Where the news and the official papers differ, the page goes by the official paper.

Where the facts come from

  1. Urban Development & Housing Department, Bihar, Guidebook on application, approval and occupancy procedure under Bihar Building Bye-laws 2014: documents list, residential fee table per sq m, 60-day timeline, 30-day objection rule, no prior inspection, empanelled architects and engineers, 3 + 2 years validity, occupancy certificate ₹1,000 in 30 days.
  2. Urban Development & Housing Department, Bihar, Bihar Building Byelaws 2026 (draft): risk matrix (Table 2), deemed permit for low-risk buildings through an empanelled third-party architect, 30-day decision for high risk, 5 + 2 years validity, plinth 0.45–0.9 m.
  3. Prabhat Khabar, Muzaffarpur: online approval in the 49 Nagar Nigam wards and its extension to 216 planning-area villages in Mushahari, Kanti, Kurhani, Marwan, Bochaha and Minapur, with no cash payment (article since removed); report on the stricter online process and ward-wise engineers and town planners.
  4. GKToday, Bihar launches UPYOG portal, 1 Nov 2026: 264 urban bodies, online building plan approval with a digital certificate.
  5. Patna Press, Tirhut township, Muzaffarpur, 26 Apr 2026: sale, purchase and construction stopped until 30 Jun 2027 in villages of Kurhani, Marwan, Kanti and Mushahari.
  6. Patna Press, Commercial building setbacks relaxed, 10 May 2026; Village multi-storey approval rules, 17 Aug 2026 (proposed).
  7. Census of India 2011: Muzaffarpur city population under 10 lakh, which sets the Nagar Nigam fee column.