Naksha pass in Muzaffarpur: who approves your plot, the papers, the fee and the 60 days
Abhishek Ranjan, Diploma Civil Engineer · checked against the Bihar UD&HD guidebook and the 2026 draft bye-laws, 13 Nov 2026
The short answer
1Find your office
2Empanelled architect draws and signs
3File with papers and fee
4Answer any objection
5Sanction, then foundation
Inside Muzaffarpur Nagar Nigam's 49 wards, the Nagar Nigam passes the naksha. In the 216 planning-area villages of six blocks, the planning authority does. Other towns of the district have their own Nagar Parishad or Nagar Panchayat. Never start the foundation on the strength of an uploaded application.
60 days
Time the rules allowFrom the date of application, under the Bihar bye-laws 2014.
₹10/m²
Nagar Nigam feeFor a house up to 10 m high, on built-up area. Village in the planning area: ₹3.
3 years
The sanction stays validThen revalidate once for 2 more years. Finish inside that.
Who passes the naksha for your plot
A sketch, not a map: block names show roughly where the planning area runs. The township patch is drawn from the villages named in news reports (Kurhani, Marwan, Kanti, Mushahari); confirm your khesra at the office.
Step 1
Find out which office your plot belongs to
Filing with the wrong office is the most common way to lose a month. The line between the Nagar Nigam and the planning area runs through villages, not along a main road.
ANagar Nigam wards
Muzaffarpur Nagar Nigam
All 49 wards of the city. Applications have been taken online here for some time, with no cash at the counter. The town-planning section, with assistant engineers and town planners given wards, scrutinises the drawing.
BPlanning-area villages
Planning authority
216 villages in Mushahari, Kanti, Kurhani, Marwan, Bochaha and Minapur blocks, next to the city. The same online system was extended to them. The fee table has its own, lower column for a gram panchayat inside a planning area.
CThe rest of the district
Town office, or no urban permit
A plot inside another town goes to that town's Nagar Parishad or Nagar Panchayat. An ordinary village outside the planning area is not covered by the urban bye-laws today. The Panchayati Raj Department was drafting rules in Aug 2026 for multi-storey buildings in villages near cities.
Not sure which side you are? Take the khata and khesra numbers and the mauza name (from your deed or the rasid) to the Nagar Nigam town-planning counter. They tell you the office in a minute. Village plot: read do I need a naksha pass in a village.
Check the township stop first. The Bihar Cabinet stopped sale, purchase and construction in the proposed Muzaffarpur township area until 30 June 2027 or until its master plan is final, whichever comes first. Villages named in reports are in Kurhani, Marwan, Kanti and Mushahari, near the airport and the new bypass. No naksha will pass there until then: which land is affected.
Step 2
The papers the office asks for
This is the list in the Bihar government's own guidebook for building plan approval. Your architect prepares the forms and drawings; the ownership papers come from you.
Paper
What it proves
Where it comes from
Application, Form II
Your request for permission
Architect fills it
Sale deed (kewala)
You own the plot
Your registry papers
Jamabandi or latest rasid
The land record is in your name
Circle (anchal) office, Bihar Bhumi online
LPC
You hold the land now
Circle office
Affidavit of peaceful possession
No dispute on the plot
Notary
Drawings, 4 setsplus PDF and CAD files
Site plan, floor plans, section, elevation
Empanelled architect or engineer
Supervision certificate, Form V
A technical person will watch the work
Architect or engineer
Structural stability, Form IV
The frame is designed safe
Engineer
Checklist, Form VI
Nothing is missing
Architect
Fire / airport NOC
Only where the rules ask
Not needed for most single houses
One plot, one size, on every paper
Katha is not the same size everywhere in Bihar. Convert with the figure your deed or circle office uses: katha, dhur, dismil to sq ft.
Step 3
The drawing: who signs it and what the office checks
The guidebook says to hire only an architect or structural engineer empanelled by the Urban Development and Housing Department through the urban bodies. Their names and registration numbers go on every sheet.
What the office checks first
Under the Bihar Building Bye-laws 2014 and amendments
Open space left at the front, back and sides (setbacks), for your road width and plot size: setback rules
Height and number of floors, and how much of the plot is covered
Room, stair and kitchen sizes, parking where it applies
The setback relief notified in May 2026 (no side gap on plots up to 10 m wide) was reported for commercial buildings. For a house, go by what your architect reads in the current rules.
Who may sign
Architect or engineer, empanelled
Empanelled architects and engineers are listed on the urban body's or the department's website.
The 2026 draft defines an empanelled architect as one registered with the Council of Architecture and empanelled with UD&HD.
A draftsman's or mason's sketch is not accepted, however neat.
Ask the architect for his empanelment number before he starts drawing.
Get the drawing made through us
Ar. Sumit Kumar, Doric Nirmaan, with Tashya
We work with Ar. Sumit Kumar for house design: floor plan, elevation, structure, electrical and plumbing sheets. Say in your first message that you need drawings for naksha pass, so the plan is made to the bye-laws from the first sketch and not fixed after a query.
60 days by the rules, and what an objection does to the clock
These are the service timelines the Bihar government notified under the 2014 bye-laws. The office does not inspect the site before approving a house plan; the drawing and papers decide it.
Stage
Time
What you do
File
Day 0
Architect uploads; you pay the fee. Keep the application number.
Scrutiny
≤ 60 days
Watch the status. Pick up the phone when the office calls.
Objectionif raised
30 + 30
Correct and resubmit within 30 days. The office then decides within 30. A second chance is given once; after that it is rejected.
Sanction
Form VIII-A
Print it. Keep a copy on site with the stamped drawing.
Build
3 + 2 yrs
Build as drawn. A new floor later needs a revised plan first.
Occupancy
30 days
Apply after completion, ₹1,000. Banks and buyers ask for it.
Which portal?Nagar Nigam applications have run online for some time. On 1 Nov 2026 Bihar launched its UPYOG portal for all 264 urban bodies, with building plan approval among its services; the national tracker still showed Bihar as being set up. Ask the town-planning counter which portal is taking applications the week you file. Your architect normally holds the login and uploads for you.
What slows it downNot the office's 60 days, but papers that disagree with each other and drawings that break a setback. One complete file beats two quick ones.
The government fee
The fee is charged per square metre of built-up area
This is the residential table in the Bihar UD&HD guidebook, in rupees per sq m of built-up area on all floors. Muzaffarpur's population is under 10 lakh (Census 2011), so the Nagar Nigam column is the "up to 10 lakh" one. The portal shows the final amount on the day.
Building height
Planning-area village
Nagar Panchayat
Nagar Parishad
Nagar Nigam
Up to 10 musually up to ground + 2
₹3
₹4
₹6
₹10
10 to 15 m
₹5
₹6
₹8
₹15
Above 15 m
₹6
₹8
₹12
₹20
Non-residential buildings pay double. If the ground floor is a shop, ask the office how it counts that floor. The architect's drawing fee, notary and copies are separate; ask him for his fee first: house design.
Built-up area: 2,000 sq ft = 186 m²
Fee by the guidebook table
Building permit fee₹1,858₹10 per m², Nagar Nigam, up to 10 m
Under the 2026 draftLow riskPlot up to 300 m² and height up to 10 m
Rates from the UD&HD guidebook under the 2014 bye-laws. Other charges the portal adds, and any later revision, are not included. 1 m² = 10.764 sq ft.
Coming, not yet law
The 2026 draft bye-laws would make most houses "low risk"
The Urban Development and Housing Department has put out a draft of new Bihar Building Byelaws 2026. On 13 Nov 2026 it was still a draft. Until it is notified, the 2014 rules and the 60 days above apply.
Residential
Low risk
Moderate
High
Height
Up to 10 m (G+2)
10–15 m
Above 15 m
Plot area
Up to 300 m²about 3,229 sq ft
300–500 m²
Above 500 m²
Route
Empanelled third-party architect submits plans, affidavit and site report; permit deemed granted, work can start
Same, plus a certificate that the plan meets disaster-safety guidelines
Objections in one go within 15 days; decision within 30 days
Valid for
5 years, plus 2 on revalidation
A building that falls in two classes counts in the higher one. More than 8 flats is always high risk. If a permit is got by false papers, it can be withdrawn.
What it means for a Muzaffarpur family
A 1 to 2 katha plot (about 126 to 253 m²) with ground + 1 or ground + 2 would be low risk.
The architect carries more responsibility: he certifies the drawing and the site. Pick one who will stand behind his signature.
Deviation from the submitted plan can be acted on. Build exactly what was filed.
When it is notified, we will update this page. Until then, file under the current rules.
What goes wrong
Four mistakes we hear about at the counter
Filed at the wrong office
Weeks go before anyone opens it
Plots on the city's edge are the usual case. Ask with your khesra number before the architect uploads.
Sizes that do not match
Objection, 30 days lost
Deed in katha, drawing in sq ft from a tape that measured differently. Settle the figure first: katha to sq ft.
Foundation on the day of upload
Building without a sanction
An application number is not a permit. If the plan then changes on objection, the footing may be in the wrong place.
Building more than was passed
Trouble with loans, sale and the occupancy certificate
Planning a floor later? Get the column and footing sizes drawn for it now, and file a revised plan before you build it.
Once the sanction is in your hand
Buy for the drawing that was passed
Order the foundation material from the sanctioned drawing and its structure sheet, not from the first sketch. Send us the sheets and we price every item at today's rate. Anything not on our shelf we can order for you; ask on WhatsApp for the time it takes.
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
How do I get a naksha passed in Muzaffarpur? (naksha pass kaise karaye)
Find the office for your plot (Nagar Nigam, planning authority, or the town's Nagar Parishad or Nagar Panchayat). Get the drawing made and signed by an empanelled architect or engineer, file it with the ownership papers and fee, answer any objection within 30 days, and start the foundation only after the sanction letter.
Is naksha pass online in Muzaffarpur?
Yes. Nagar Nigam applications have been online for some time, and the planning-area villages were added later. Bihar's UPYOG portal, launched on 1 Nov 2026 for all 264 urban bodies, lists building plan approval among its services. Ask the town-planning counter which portal is live when you file; the architect usually uploads.
What documents are needed for naksha pass?
Form II, 4 sets of drawings with PDF and CAD files, sale deed, jamabandi or rasid, LPC, an affidavit of peaceful possession, Form V (supervision), Form IV (structural stability), Form VI (checklist) and the fee. Fire and airport NOCs only where they apply.
How long does naksha pass take?
60 days from the application under the 2014 rules. An objection gives you 30 days to resubmit, and the office decides within 30 days after that.
What is the naksha pass fee?
By the guidebook table, ₹10 per sq m of built-up area in the Nagar Nigam for a house up to 10 m high, ₹3 in a planning-area village. A 1,000 sq ft ground plus 1,000 sq ft first floor is about 186 m², so about ₹1,858 in the Nagar Nigam. The portal shows the final figure. More: naksha pass fees.
Do I need a naksha pass for a house in a village?
Yes in the 216 planning-area villages and inside any Nagar Parishad or Nagar Panchayat. Ordinary villages outside these are not under the urban bye-laws today. See village naksha pass.
Who can sign my naksha drawing?
An architect or engineer empanelled with the Urban Development and Housing Department through the urban bodies; the list is on their websites. We can put you in touch with Ar. Sumit Kumar of Doric Nirmaan: about him.
I want to add a floor later. Does the first sanction cover it?
No. The sanction covers what was drawn. File a revised plan before building the new floor, and have the footing and columns designed for it from the start, so the revision is only paperwork.
Abhishek Ranjan
Diploma Civil Engineer, Tashya Ventures
Answers cement, steel and building questions at our Reva Road store, Muzaffarpur. The steps, timelines and fees on this page are from the Bihar Urban Development and Housing Department's guidebook and the 2026 draft bye-laws, read on 13 Nov 2026. Where the news and the official papers differ, the page goes by the official paper.
Urban Development & Housing Department, Bihar, Bihar Building Byelaws 2026 (draft): risk matrix (Table 2), deemed permit for low-risk buildings through an empanelled third-party architect, 30-day decision for high risk, 5 + 2 years validity, plinth 0.45–0.9 m.
Prabhat Khabar, Muzaffarpur: online approval in the 49 Nagar Nigam wards and its extension to 216 planning-area villages in Mushahari, Kanti, Kurhani, Marwan, Bochaha and Minapur, with no cash payment (article since removed); report on the stricter online process and ward-wise engineers and town planners.
GKToday, Bihar launches UPYOG portal, 1 Nov 2026: 264 urban bodies, online building plan approval with a digital certificate.
Patna Press, Tirhut township, Muzaffarpur, 26 Apr 2026: sale, purchase and construction stopped until 30 Jun 2027 in villages of Kurhani, Marwan, Kanti and Mushahari.