Electrical check before plaster: pipe routes, box depths, the earth wire run, and a photo of every wall
- 1Pipe routes: every point has a pipe, runs go straight, no more than four bends between boxes, a pull wire in each.
- 2Box depths: each box face sits where the plaster face will be, or the tile face on tiled walls.
- 3Earth wire run: a pipe from the earth pit to the DB, and every pipe big enough for three wires.
- 4Photos: one of each wall, room name chalked on it, sent to us on WhatsApp and kept for life.
Wire, switches and the board can all be changed after plaster. These four can't, without cutting the new wall. Walk every room with your electrician and this sheet. It takes about an hour for a two-room floor.
This is stage 2 of our four-stage wiring checklist, done in full. Wire sizes and MCBs come later, after plaster: wire amps chart · which MCB for which load. The ten mistakes we see most: common wiring mistakes.
Pipe routes
A diagonal pipe, or a run with six bends. The diagonal gets a nail through it the day someone hangs a TV. The six-bend run jams halfway when the wire is pulled, and by then the wall is plastered: the only fixes are cutting a new groove or a surface casing.
How many wires fit in one pipe
| Wire size | 20 mm pipe | 25 mm pipe | So, per pipe |
|---|---|---|---|
| 1.5 sq mm | 4 wires | 8 wires | 20 mm: one light circuit · 25 mm: two |
| 2.5 sq mm | 3 wires | 6 wires | 20 mm: one socket circuit, full · 25 mm: two |
| 4 sq mm | 2 wires | 5 wires | An AC line on 4 sq mm needs 25 mm |
CPWD Table I, the column for pipes with bends. Three wires per circuit: phase, neutral, earth. Pipe size is the outside diameter printed on the pipe.
Box depths and positions
A box set to the brick, not the plaster line. After plaster it sits 12 mm deep in a hole; on a tiled wall, 25 mm. The plate rocks, the screws are too short, and moving the box means cutting fresh plaster or tiles around it.
The earth wire run
No pipe left for the earth lead. It ends up clipped along the outside wall, where a mason's trowel or a rusty clip cuts it one day, and the whole house's earth hangs on that one wire. Nothing shows until a geyser body goes live and the RCCB has nothing to work with.
Photos of every wall, on WhatsApp
Photos taken the morning after the first coat. They show grey plaster and nothing else. The photo has to be taken the evening before, and it is free.
Send us what's still open
We'll look at the unticked items and your wall photos with you, and send any pipes, boxes or bends still needed with today's price.
Your ticks stay on this phone only. Nothing is sent until you press the button. The printed sheet has lines for the electrician's and your signature.
What the walk usually turns up short
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Conduit pipe, 20 and 25 mmFor the missed point and the spare runsAsk today's rateper length Bends, couplers, junction boxesGentle bends, and a box where a run has too manyAsk today's rateper piece Metal switch boxes2 to 12 module · with earth studAsk today's rateper piece V-Guard Classo+ green wireThe earth lead and every circuit's earthAsk today's rateper coil PVC insulation tapeOpen pipe ends sealed before plasterAsk today's rateper roll Whole-house wiring kitPipes, boxes, wire and board on one billAsk today's rateper kitGI pull wire, wire mesh strip for grooves, a DB box with spare ways, or anything not shown: we can order it for you; ask on WhatsApp for the time it takes. Today's prices: electrical rates.
Short answers
What has to be done before plaster? (plaster se pehle kya karein)
Everything that sits inside the wall: every pipe and box in place, the pipes straight and not over-bent, a pull wire in each run, boxes set to the plaster face, the pipe for the earth lead laid, and a photo of each wall. Wire, switches and the board come after plaster.
How deep should the switch box be set?
So its front edge is level with the finished wall. CPWD's specification says switch boxes are mounted flush. With inside plaster of about 12 mm, the box stands about 12 mm in front of the brick; on a wall getting tiles, about 25 mm, to meet the tile face. Both are usual practice: ask your mason what thickness he will plaster.
How many wires go in a 20 mm pipe?
CPWD's table for pipes with bends: four of 1.5 sq mm, three of 2.5 sq mm, or two of 4 sq mm. A circuit is three wires with the earth, so a 20 mm pipe takes one light or one socket circuit. For two circuits, or an AC line on 4 sq mm, use 25 mm. 20 or 25 mm
Does the earth wire go in the same pipe?
Yes. CPWD's specification has the earth wire drawn inside the pipe of every circuit and ended on the earth terminal in the switch box, and IS 732 makes it the same size as the phase. That is why the pipe size has to allow for it now. Sizes: wire amps chart · MCBs: which MCB for which load.
Something was missed and the wall is already plastered. What now?
Fix it before putty, not after paint. A short groove cut in fresh plaster and patched costs a day; after putty and paint it costs a repaint of that wall. If cutting isn't possible, the run goes on the surface in a casing. Concealed or surface
Is a mesh strip over the grooves needed?
It is usual practice, not a code rule. Plaster over a filled groove often cracks along the pipe line as it dries; a strip of wire mesh nailed across the groove before plaster holds it. Ask your mason; we can order the mesh.
Will you come to the site to check?
We don't promise site visits. Send photos on WhatsApp before plaster, one per wall with the room name chalked on it, and we will look at them with you.
Looks after wires, switchgear, inverters and pumps at our Reva Road store, Muzaffarpur. The figures on this page were checked on 13 Nov 2026 against CPWD's General Specifications for Electrical Works and IS 732. Where a figure is our usual practice rather than a rule, the page says so.
Where the figures come from
- Central Public Works Department, General Specifications for Electrical Works, Part I (Internal), 2013: 3.15 (switch box bottom 1.25 m from floor), 4.2.3 (metal boxes at least 1.2 mm / 18 gauge; earth stud in each box), 4.3.3 (pipes buried before plastering; switch boxes flush with the wall; GI fish wire 1.6 or 1.2 mm), 5.2.3 (PVC boxes: 2 mm walls, at least 60 mm clear depth), 5.3.1 (joints cemented, no damaged pipe; bend radius at least 7.5 cm; not more than four quarter bends outlet to outlet), 5.3.3 (fixing in the chase at most 60 cm apart, 15 cm either side of a bend), 5.3.4 (earth wire drawn inside the pipe in every circuit), Table I (wires per pipe).
- IS 732 (code of practice for electrical wiring installations): earth wire the same size as the phase wire.
- Plaster thickness (about 12 mm inside, 18 mm outside, about 25 mm for plaster plus wall tile), box heights, straight runs, mesh over grooves and the photo method: usual practice in Muzaffarpur houses, labelled as such on the page, and the same figures our other pages use.
Send us your wall photos
Sashikesh will look at them with you before the plaster mason starts, and send anything still needed with today's price on WhatsApp.