Wiring checklist for a new house: what to check before the slab, before plaster, before putty, and at the end
- 1Before the slab is cast: pipes, ceiling boxes and fan boxes. No wire yet.
- 2Before plaster: every wall box and pipe in place, level and flush.
- 3Before putty: wire pulled, board wired, earth joined, insulation tested.
- 4After paint: switches, sockets and fans fitted, then every test before the last payment.
Each stage buries the one before it: concrete, then plaster, then putty and paint. A miss found at the next stage means breaking something. So the check happens on the day before, not after.
Before the slab is cast
No fan box, or no pipe for the AC, "we'll decide later". After dhalai the only ways are to cut the slab, which weakens it, or run an ugly pipe on the ceiling. A fan hung on a hook knocked into old concrete is how fans fall.
The full list for slab day, with counts: conduit before slab casting · the rest of the slab (steel, cover, shuttering): chhat dhalai checklist
Before plaster
Boxes fixed before the guide strips. The box ends up deep inside the plaster or sticking out, and later the switch plate rocks, or the screws don't reach. Re-setting a box after plaster means cutting the new wall around it.
A printable one-page sheet for this day: electrical check before plaster
Before putty
Pulling two wires to save a coil. The house works fine, and the socket earth leads nowhere. The first time a geyser body goes live, nothing trips, and the person touching it is the path. Pulled now, the earth wire costs one coil; pulled later, it means emptying every pipe.
How many coils of each size: wire coils for a house · when the painter can start after this: putty, primer, paint
Final: after paint, before the last payment
Paying the last instalment before the tests. Once the electrician is paid and gone, a socket with no earth or an RCCB that never trips stays that way until the day it matters. Hold the last payment until every line above is ticked.
The final test in more detail: final electrical test · ten mistakes we see: common wiring mistakes
Send us what's still open
We'll look at the unticked items with you, and send the material for the next stage with today's price. Photos of each wall help.
Your ticks stay on this phone only. Nothing is sent until you press the button.
What to buy, and when to buy it
Buy each stage's material a few days before that stage, not all on day one. Then wire isn't lying on site through the plaster, and switches don't sit in a room while it's painted. Quantities: wire coils for a house or the wiring calculator.
| Before | Buy | From us |
|---|---|---|
| 1 · Slab | 20 and 25 mm conduit, bends, couplers, circular boxes, fan boxes with rod, end caps, earthing materialEarth rod or plate and earth wire for the pit | Conduit · circular boxes · fan box with rod |
| 2 · Plaster | More conduit for the walls, metal boxes by module size, DB boxOne box per board, sized with one spare module | Metal boxes · bends, elbows, tees |
| 3 · Putty | Wire coils by size, MCBs, DP main, 30 mA RCCB, PVC tapePhase, neutral and earth of each size | V-Guard Classo+ · UltraBolt · Elegna MCB · PVC tape |
| 4 · Final | Switches, sockets, plates, regulators, indicator, fans, lightsCount modules per board first | Torio switches · sockets · plates · Haize VX fan |
Want it all on one bill? Whole-house wiring kit. Send us your naksha and we'll make the list: wiring estimate service.
Everything the four stages use
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Conduit pipe, 20 and 25 mm3 m lengths · slab and wall runsAsk today's rateper length Circular boxOne at every ceiling lightAsk today's rateper piece Fan box with rodOne at every fan centre, rod tied to steel₹ 132per piece Metal switch boxes2 to 12 module · one spare module per boardAsk today's rateper pieceAnything not shown, any size, model or accessory: we can order it for you; ask on WhatsApp for the time it takes. Today's prices: electrical rates · wire price list.
Short answers
When should wiring be done in a new house? (wiring kab karwayein)
In four steps that follow the building. Pipes and boxes go in before the slab is cast and before the walls are plastered. Wire is pulled after plaster and before putty. Switches, sockets and fans go on after the last coat of paint, followed by the tests.
Is wire put in the slab before casting?
No. Only the conduit pipes, circular boxes and fan boxes go into the slab. Wire is pulled through the pipes much later, after plaster, so the pipes must be continuous, capped at the ends and fitted with a pull wire.
Can wiring be done after plaster?
Wire pulling is done after plaster. Pipes and boxes are not: if they were missed, the new plaster has to be cut and patched, or the wire runs on the surface in a casing. That is why the check before plaster matters most for the walls. Concealed or surface wiring
Is an RCCB compulsory in a house?
Yes. The Central Electricity Authority's safety regulations of 2023 (regulation 44) say an installation must be controlled by a residual current device, and for a home its operating current must not exceed 30 mA. Fit a 30 mA double-pole RCCB after the main switch. MCB vs RCCB
Do all sockets need earthing?
Yes. For new or renovated installations the CEA regulations (43) say all plug sockets must be three-pin, with the third pin permanently earthed. So a green earth wire, the same size as the phase wire, runs with every circuit.
When should switches and plates be fitted?
After the last coat of paint has dried. Fitted earlier, they get paint on them, the painter cuts around them, and the plates are taken off and put back with dust in the boxes.
Who should do the wiring?
The CEA regulations (31) say house wiring is to be done by an electrical contractor licensed by the state government. It matters at the end: before NBPDCL connects the house, it either tests the wiring itself or accepts test results signed by a licensed contractor (regulation 33).
Will you come to the site to check?
We don't promise site visits. Send photos on WhatsApp before dhalai and before plaster, one per room or wall, and we will look at them with you.
Looks after wires, switchgear, inverters and pumps at our Reva Road store, Muzaffarpur. The rules on this page were checked on 13 Nov 2026 against the Central Electricity Authority's 2023 safety regulations and V-Guard's own sheets. Where a figure is our usual practice rather than a rule, the page says so.
Where the rules come from
- Central Electricity Authority, (Measures relating to Safety and Electric Supply) Regulations, 2023, Gazette of India, 8 June 2023: reg. 31 (work by a state-licensed electrical contractor), 33 (installation tested by the supplier, or results signed by a licensed contractor accepted, before supply), 35 (insulation resistance checked before connection), 43(viii) (new or renovated installations: all plug sockets three-pin, third pin earthed), 44 (residual current device; in homes, not more than 30 mA).
- V-Guard, Classo+ house wire product page: current in conduit 1.5 sq mm 13 A, 2.5 sq mm 18 A, 4 sq mm 24 A, the figures behind the MCB rule.
- V-Guard, Elegna MCB technical specification: SP and DP, 6 to 63 A, B and C curve.
- IS 732 (code of practice for electrical wiring installations): earth wire the same size as the phase wire; insulation tested at 500 V between each conductor and earth.
- Pipe sizes, box heights, spare wire in boxes and the order of work: usual practice of electricians in Muzaffarpur, labelled as such on the page.