Brick walls carry the roof
The usual one-storey Bihar house: 9-inch walls, an RCC slab, a plinth band and a lintel band.
This is the same house as on our cement for 1000 sq ft page, with 96 bags in the 5-inch M20 roof slab. Add about 5% for loss on site. These are planning figures to budget and to order stage by stage. They are not a bill of quantities; your drawing decides.
The cft-per-sq-ft rules builders use, and what our worked house comes to. Count the built-up area of every floor; what "1000 sq ft" means is explained on the cement page.
The usual one-storey Bihar house: 9-inch walls, an RCC slab, a plinth band and a lintel band.
Column footings, columns and beams at plinth and roof are extra concrete, so gitti goes up most. The walls are still there.
Plinth filling is outside all of these. The per-sq-ft rules are standard planning figures, the same ones our house construction cost calculator uses.
Every lot below comes from the cement count of the same house, turned into balu and gitti by its mix. The table also says when each lot should reach the site.
| Stage and what goes in it | Balu | Gitti | Trolleys, when |
|---|---|---|---|
| 1 · Neev and plinthPCC bed 6″, 1:4:8 · brick footing and plinth wall, 1:6 · plinth band 6″, M20 | 480 | 325 | 5 balu + 3½ gittiGitti and balu for the PCC bed before the digging ends; the rest as the footing rises. |
| 2 · Walls up to the roof9″ and 4.5″ brickwork · lintel band · chhajjas | 370 | 85 | 4 balu + 1 gittiIn lots as the walls rise. The gitti a day before the lintel band. |
| 3 · RoofSlab 5″, M20, 96 bags · stair · parapet | 230 | 391 | 2½ balu + 4 gittiAll the slab's 177 balu and 354 gitti on site two days before the dhalai. A slab is poured in one go. |
| 4 · PlasterInside 12 mm 1:6 · outside 18 mm 1:4 · ceiling 8 mm 1:3 | 285 | — | 3 baluRoom by room, sieved lal balu. Keep a little extra for uneven walls. |
| 5 · FloorPCC 3″, 1:4:8 · tile bed 20 mm, 1:4 · plinth protection outside | 209 | 290 | 2 balu + 3 gittiAfter the filling has settled, before tiling. |
| Whole houseAdd about 5% for loss: about 1,650 cft balu and 1,145 cft gitti to plan for. | 1,574 | 1,091 | 16 + 11 |
| Plinth fillingBetween the plinth walls, after the plinth band, before the floor PCC | 2,250 | — | 22–23Local balu or good soil. Below. |
The bag counts for each stage, and why the slab is 96 bags, are on cement for 1000 sq ft and cement for a chhat dhalai. For one part of your own drawing, use the cement, sand and gitti calculator.
Online counts for "sand for 1000 sq ft" leave the filling out. In Muzaffarpur, where houses sit on raised plinths, it is often the biggest order on the site.
About 90% of the floor area × the plinth height. The walls take the other tenth. Standard planning figure, for 1000 sq ft:
| 1.5 ft plinth | 1,350 cft |
| 2 ft | 1,800 cft |
| 2.5 ft | 2,250 cft |
| 3 ft | 2,700 cft |
| 4 ft | 3,600 cft |
Fine local balu or good soil from the site. Not lal balu: that is money spent where no strength is needed. Usual practice is layers of about 6 inches, each watered and rammed, so the floor does not sink and crack later. Which fill, and how: plinth bharai, balu or mitti.
Soil dug out of the footing trenches goes back in, so you buy less than the table. Fill settles when watered, so order about a tenth more than the space (usual practice). A higher plinth for floods adds 900 cft for every foot: how high in a flood area.
Anti-termite treatment goes into the soil before and during the filling, not after the floor is laid: termite treatment.
Order by kind, not just by cft. Fine sand in a slab weakens it; lal balu in the filling wastes money.
Coarse sand for every concrete (PCC, bands, slab, stair, floor) and, sieved, for plaster and the tile bed. This is the sand to book early. Which grain for plaster and which for dhalai: kaun si balu.
For brickwork. Sand for masonry mortar has its own standard (IS 2116), apart from concrete sand, and may be finer. Clean local balu does the job; lal balu is the safer choice for the footing. Never fine sand in concrete.
Slab, plinth and lintel bands, chhajjas, stair: everything with sariya in it. Stone gitti only; RCC takes no brick ballast. More on sizes: gitti.
The PCC bed under the footing and the floor PCC. Many Bihar sites use jhama, broken over-burnt brick, here; CPWD's specification allows 40 mm brick aggregate from well-burnt or over-burnt brick. That takes about 480 cft off the stone gitti.
Nobody is cheating. Each of these moves the count, and the last three are where cft go missing after you have paid.
The brick footing and the plinth wall sit underground and inside the plinth. A count that starts at floor level misses them. Ours includes them.
Our 285 cft is the straight arithmetic. UltraTech's own plaster figure is well above it because real brick faces are not flat (worked out on the cement page). Straight brickwork saves plaster sand.
Ask the thekedar which he plans before comparing gitti figures. One count with jhama and one without can both be right.
Damp sand swells, which engineers call bulking. A wet trolley holds less real sand, and a ghamela-measured mix with wet sand ends up short of sand. How to allow for it: geeli balu.
100 cft is the usual count, but trolleys differ. Length × width × level height, in feet, and pay per cft: how many cft in a trolley.
A heap on mud loses its bottom layer. Rain washes sand into the drain. Loose heaps by the road walk away at night. That is why we say order by stage.
Put in your area, floors, slab and plinth. It scales the worked house above and works the slab and filling out exactly. For one part of the drawing, use the full calculator.
Planning figures, not a bill of quantities. Prices are filled in from today's rate per cft. Delivery is charged separately; ask for the amount for your site (delivery). Cement for the same house: cement count.
The rest of the same house: cement for 1000 sq ft · sariya kitna lagega · bricks for 1000 sq ft · the whole budget: cost of a 1000 sq ft house.
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Lal baluCoarse · concrete, slab, plasterAsk today's rateper cft Local baluFine · brick mortar, plinth fillingAsk today's rateper cftWe sell genuine material with a GST bill: 5% on sand and gitti. Anything not on the shelf, we can order for you; ask on WhatsApp for the time it takes. Today's prices: balu, gitti, eent rate · cement rate.
For one storey with brick walls and an RCC roof, about 1,575 cft of balu, about 16 trolleys of 100 cft, before the plinth filling. The planning range is 1,300 to 1,800 cft. Add about 5% for loss on site.
About 1,090 cft if every concrete uses stone gitti: about 535 cft of 20 mm and 556 cft of 40 mm. With jhama in the foundation bed and floor PCC, stone gitti drops to about 610 cft. An RCC frame house takes 1,000 to 1,350 cft.
About 16 to 17 trolleys of 100 cft for the house, with loss. Then the plinth filling: about 13½ trolleys for a 1.5 ft plinth, 22½ for 2.5 ft and 27 for 3 ft, less whatever soil from the trenches goes back in.
A 5-inch M20 slab: about 96 bags of cement, 177 cft of balu and 354 cft of gitti, so about 2 trolleys of balu and 3½ of gitti. 4-inch: 77 bags, 142 cft balu, 284 cft gitti. 6-inch: 115 bags, 212 cft balu, 424 cft gitti. The rest of the dhalai order: chhat dhalai cement.
By the arithmetic, about 45 cft for 12 mm inside plaster at 1:6, and about 63 cft for 18 mm outside plaster at 1:4. Uneven brick walls can take half as much again.
No. With 1000 sq ft on each floor, about 2,520 cft of balu and 1,570 cft of gitti, because the foundation, plinth and ground floor PCC are made once, and the filling does not grow. The engineer makes the foundation bigger for two floors, so plan near the top of the range.
No. Jhama is for the PCC bed and the floor PCC only. Anything with sariya in it takes stone gitti, usually 20 mm.
One cubic metre is about 35.3 cft, so a 100 cft trolley is about 2.83 m³. The house's 1,575 cft of balu is about 45 m³; its 1,090 cft of gitti is about 31 m³.
Yes, 5% on both, shown on the bill with the cft and the rate.
Civil engineer at our Reva Road store, Muzaffarpur. He worked the balu and gitti out of the same house as our cement page on 13 Nov 2026, using UltraTech's mix figures and standard estimating figures. Where the figures disagree, the page says so and uses the safer one.
We'll count the balu and gitti for each stage, with today's rate per cft and the delivery charge, on WhatsApp. Send photos of the sariya before dhalai and we'll look at them with you.