Pipe on the plate, under the bars
Concrete can't get under it, so the pipe shows through or cracks a line along the ceiling.
All of it goes on the day before dhalai, after the steel is tied. Once the concrete is in, nothing can be added to the slab. A missing pipe becomes a casing on the ceiling; a missing fan box becomes a fan on a drilled hook.
The mason, the plumber and the electrician all work on the same shuttering in the same few days. Check each list against its own page.
For the whole house in four stages (slab, plaster, putty, final), see the new house wiring checklist. Steel for the slab: how much sariya in the chhat.
A pipe not taken to a fan or an AC "because we'll decide later". The slab can't be opened later without weakening it. What's left is a fan clamp in drilled holes and a casing across the ceiling. A spare pipe costs very little today.
Already past this stage? The wall check before plaster is on electrical check before plaster; what goes wrong later is on ten wiring mistakes in new houses.
Count the wires in each run before choosing the pipe. In the bedroom drawn above, every switched point sends its own phase wire back to the board, and a neutral and an earth go with them.
| Run | Wires inside (1.5 sq mm) | Pipe |
|---|---|---|
| Board drop → L1 | L1, fan and L2 phases + neutral + earth = 5 | 25 mm |
| L1 → fan | Fan and L2 phases + neutral + earth = 4 | 20 mm |
| Fan → L2 | L2 phase + neutral + earth = 3 | 20 mm |
| Board → AC drop | Phase, neutral, earth in 2.5 or 4 sq mm | 25 mm |
CPWD's Table I: a 20 mm pipe with bends holds four 1.5 sq mm wires or three of 2.5 sq mm; a 25 mm pipe holds eight and six. A 4 sq mm AC line goes in 25 mm. Pulling more than that tears the insulation on the way in.
| Item | Count | Note |
|---|---|---|
| Fan box with rod | 1 | At the fan centre |
| Round box | 2 | 25 mm 2-way at L1, 20 mm end box at L2 |
| Conduit 20 mm | 2 lengths | 3 m each; runs of about 1.8 m plus offcuts |
| Conduit 25 mm | 1 length | Board drop to L1 (add 2 for the AC run) |
| Long bend, couplers, reducer | 1 + 3 + 1 | Bend at the drop; 25×20 reducer at L1 |
| End caps or tape | 2 | Board drop and AC drop |
| GI fish wire, 16/18 SWG | about 7 m | Every run, a hand-length spare at each end |
Usual practice counts; your electrician fixes the final number from your naksha. A hall with two fans and four lights takes roughly double. For the whole slab, use the list maker below.
Put in the numbers for the slab you are casting next. It works out the slab material and writes the message to us.
Estimate from usual practice: about 1.8 m of 20 mm pipe between points in a room, 2 m of 25 mm from each board to its first box, 4 m per AC run, 10% for offcuts. Reducers: one per room. Nothing is sent until you press the button.
Curing starts the next morning: tarai after dhalai. If a run is found blocked and can't be cleared, the choices are on concealed or surface wiring.
Each of these is easy to put right with the shuttering still up, and costly or impossible afterwards.
Concrete can't get under it, so the pipe shows through or cracks a line along the ceiling.
Near the board three or four runs arrive together and get piled up, eating the slab's depth at one spot.
The most common reason a run is dead after the slab. Box entries and broken couplers let slurry in too.
Measured from the shuttering edge or a column, the fan ends up a hand-span off the middle of the room, and stays there.
Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.
Conduit pipe, 20 and 25 mm3 m, LMS and MMS · MMS for the slabAsk today's rateper length Round (circular) boxes20 and 25 mm · 2, 3 and 4-wayAsk today's rateper piece Fan box with rodOne at every fan centre₹ 132per piece Long bends, couplers, tees20 mm long bend, 25 mm elbow and teeAsk today's rateper piece PVC insulation tapeBox faces and pipe ends sealedAsk today's rateper roll Whole-house wiring kitPipes, boxes, wire and board on one billAsk today's rateper kitEnd caps, 25×20 reducers, deep junction boxes, GI fish wire and anything else not shown: we can order it for you; ask on WhatsApp for the time it takes. Cement, sariya and the rest of the pour on one order: slab-day kit. Count for the whole house: wiring calculator. Cutting and delivery are charged separately; ask for the amount for your site (delivery). Today's prices: electrical rates.
Only pipes and boxes: conduit along every light and fan run, a round box at each light, a fan box with rod at each fan, drops at each switch board and AC, all tied to the steel and sealed. No wire goes in the slab; it is pulled through the pipes after plaster.
20 mm is the smallest CPWD allows and does for runs with up to four 1.5 sq mm wires. Use 25 mm for the run from the board to the first box (it usually carries five or more), for AC lines and for spares. 20 vs 25 mm conduit
Single pipes spread out in one layer, on the bottom bars, are normal practice. The trouble is pipes bunched or stacked at one spot, or run along a beam or close to a column. Show the layout to your engineer if runs have to cross or crowd near the board.
After the steel is tied and checked, a day or two before the pour, so there's time to fix anything and the mason doesn't walk on finished runs. Book him for the pour day too.
On the bottom bars, tied with binding wire. Only the box faces sit on the plate. A pipe on the plate under the bars has no concrete below it and often shows as a crack line on the ceiling.
There is no proper fix inside the slab. The workaround is a fan clamp fixed with anchor fasteners by someone who knows the slab, with the wire in casing. See wiring mistakes in new houses.
We don't promise site visits. Send photos on WhatsApp before dhalai, one per room with a tape in the picture, and we will look at them with you.
Your ticks from the check go into the message, so we can see what's left before the pour.
Your ticks stay on this phone only. Nothing is sent until you press the button.
Looks after wires, switchgear, inverters and pumps at our Rewa Road store, Muzaffarpur. The figures on this page were checked on 14 Nov 2026 against CPWD's General Specifications for Electrical Works. Where a figure is usual practice rather than a rule, the page says so.
One photo per room with a tape in it, the day before dhalai. Sashikesh will look at them with you and send anything short with today's price.