हिंदी Call90310 74624
Home›Kits›Cement and steel
Slab-day kit · one order

Chhat dhalai kit: everything for the slab in one order, sized to your roof

For a 1000 sq ft roof, 5 inch thick
  • 96 bags cement
  • 1.3–1.4 t sariya
  • 177 cft balu
  • 354 cft gitti

Plus about 14 kg of binding wire, 250 cover blocks and 2,400 litres of mixing water, with WP+200 and a tarpaulin if you want them. Put in your own roof below and the list resizes, bar for bar and bag for bag. It comes in two deliveries: steel a week before, the rest two days before.

77/96/115
Bags per 1000 sq ftAt 4, 5 and 6 inch. M20, 1:1.5:3.
25 L
Most water per bagStandard figure for slab concrete.
2 lots
Steel first, then the restCutting and delivery charged separately.
The kit for a 40 × 25 ft roof, 5 inch
Everything in a chhat dhalai kit for a 1000 sq ft, 5 inch roof, drawn as it lands on site 96 bags + 2 spare · on planks, covered 1.3–1.4 t sariya, 12 m bars · 10% for laps in 14 kg binding wire 250 cover blocks Balu 177 cft about 2 trolleys Gitti 354 cft about 3½ trolleys 2,400 L water, 25 L a bag WP+200 20 L, if chosen Tarp for rain Lot 1, a week before Lot 2, two days before Water is from your site
Steel is the 40 × 25 ft roof worked bar by bar in how much sariya for a roof slab. Trolleys at the usual 100 cft. Beams, chhajja and stairs are extra.
Size your kit

Your roof in, the whole order out

Length and width, or the area if you know it, and the thickness from your drawing. Choose the cement and how the steel is drawn. Every line can be switched off, and the WhatsApp button sends the list split into the two deliveries.

or, if you know the roof area:

Add to the kit
Roof area: — sq ft · Not sure of the thickness? Your drawing gives it; 5 inch is common for a house.

Your chhat dhalai kit

Lot 1 about a week before

Prices are from our latest bill and change often. Please confirm today's rate on WhatsApp or call before buying.

Sariya 10 mm
——Ask today's rate per kg · Tata Tiscon or Saluja Gold
Sariya 12 mm——Ask today's rate per kg
Sariyayour listSend your engineer's bar list on WhatsApp; we weigh out exactly that, cut if you ask.
Sariya 8 mm, for chairs——Ask today's rate per kg
Binding wire—About 1 kg per quintal of bars (usual practice).Ask today's rate per kg
Cover blocks, 20 mm—About one per 4 sq ft, a 2 ft grid under the bottom bars (usual practice). We can order them for you.Ask today's rate each
Lot 2 about two days before
UltraTech Super, 50 kg—M20 at 1:1.5:3, dry volume = wet × 1.54 (usual practice).Ask today's rate per bag
Spare bags—So a short count never stops the pour halfway.
Lal balu——Ask today's rate per cft
Gitti, 20 mm——Ask today's rate per cft
UltraTech WP+200——Ask today's rate per can
TarpaulinreminderTo cover finished strips if rain comes. We can order one for you.
Mixing water, from your site—25 L a bag at most. Store twice this for washing and the first curing.
Material totalAsk rate
Send this kit on WhatsApp

Plain slab of even thickness. Your engineer's bar list overrides the kit's steel. Prices are filled in from today's rate. Cutting and delivery are charged separately; ask for the amount for your site (delivery). Beams, chhajja or stairs in the same pour: cement, sand and gitti calculator.

Two deliveries

Steel a week before, the rest two days before

When each lot reaches your site
Timeline: list sent about ten days before, lot one a week before, lot two two days before, dhalai, curing from the next morning LOT 1 Sariya, binding wire, cover blocks, chairs LOT 2 Cement, balu, gitti, WP+200, tarpaulin −10 d−7 d−2 dDAY+1 Kit list onWhatsApp Bars tied, photossent to us Counted, on planks,covered Dhalai,first light Curingbegins Book each trip at least the day before · cutting and delivery charged separately
Days are counted back from the dhalai. Material that arrives on the morning of the pour never gets checked.

Lot 1, about a week before. The bars have to be on site early, because the mason needs days to cut, bend and tie the mesh, and you need time to check it before concrete covers it. Bars come as 12 m lengths or cut to your sizes; a 12 m bar does not fit a pickup, so it travels on a longer vehicle (cutting and delivery). Once the mesh is tied, send us photos on WhatsApp before dhalai and we will look at them with you.

Lot 2, about two days before. Cement, balu and gitti arrive with time to count the bags off the truck, stack them on planks under cover and keep the sand off the mud, but not so early that cement sits for a week on a damp site. If the dhalai falls between mid-June and mid-October, book the balu early: river sand mining in Bihar stops in those months (balu rate and the June rise).

What to check in that week, and on the day, is in the chhat dhalai checklist. This page only makes sure nothing on that list is missing from the order.

No hidden sums

How each line of the kit is worked out

Each rule is labelled: a standard, a maker's figure, or usual practice on Bihar sites. The full working for cement and steel is on the guide pages linked, so it is not repeated here.

LineRule used1000 sq ft, 5 inch
CementM20 at 1:1.5:3, wet volume × 1.54 for dry, one part in 5.5 is cement, 0.0347 m³ a bag. 77, 96 and 115 bags at 4, 5 and 6 inch. Which bag and why: cement for chhat dhalai.
Usual practice
96 bags + 2
Balu, gitti1.5 and 3 parts to the cement's one, in cft; trolleys at 100 cft, rounded up to the half. Per stage for the whole house: balu and gitti for 1000 sq ft.
Usual practice
177 + 354 cft
WaterAt most 25 litres per 50 kg bag, so the mix stays strong; less if the balu is wet.
Standard figure
2,400 L
SariyaScaled from a 40 × 25 ft roof worked bar by bar: 10 mm at 6 inch both ways = 1,314 kg; 12 mm main at 6 inch with 10 mm at 8 inch = 1,403 kg. Top bars over beams and 10% for laps, bends and cut ends are inside. Weights per metre from IS 1786. Your own spacing: sariya for a roof slab.
Standard weights Worked example
1.3–1.4 t
Binding wireAbout 1 kg for every quintal of bars.
Usual practice
14–15 kg
ChairsOnly if the drawing shows them: about one per square metre under the top bars, each about 0.6 m of 8 mm bar.
Usual practice
about 22 kg
Cover blocks20 mm under the bottom bars (IS 456, inside a house), about one per 4 sq ft.
Standard cover Usual spacing
about 250
WP+200200 ml per 50 kg bag, mixed into the second half of the water. Packs of 1, 5, 10 and 20 L. More: waterproofing in the dhalai.
UltraTech
19.2 L, one 20 L can

The 3.5 to 5 kg of steel per sq ft you see online is for a whole house, footings to roof (JSW Neosteel). For the roof slab alone it would buy about three times too much. Whole-house steel by stage: sariya calculator.

Outside the kit

What the kit leaves to the site, and to later

Shuttering, props, mixer, vibrator

The thekedar or shuttering contractor brings or hires them. Book them by date and time, with a spare vibrator needle and fuel for the day.

Conduits, fan boxes, pipe sleeves

They go on the mesh before the pour, from the electrician and plumber's lists: conduit before casting · pipe sleeves in the slab.

Roof coating

Hi-Flex goes on after the slab is cured and dry, weeks later, not on dhalai day: waterproofing in the dhalai.

The rest of the house

Bricks, neev, plaster, paint and fittings, stage by stage: material list for a new house · lenter stage material.

Questions people ask us

Short answers

Dhalai ke liye kya kya chahiye? (What does a slab need from the shop?)

Cement, sariya, binding wire, balu, 20 mm gitti, cover blocks, and if you want them, chairs bent from 8 mm bar, WP+200 for the mix and a tarpaulin in case of rain. Water, shuttering, props, the mixer, the vibrator and the labour come from the site and the thekedar.

How much material for a 1000 sq ft chhat dhalai?

For a 5 inch M20 slab: about 96 bags of cement, 177 cft of balu, 354 cft of gitti and 2,400 litres of mixing water. Sariya about 1.3 tonnes with 10 mm bars or 1.4 tonnes with 12 mm main bars, plus 14 to 15 kg of binding wire and about 250 cover blocks. At 4 inch the cement is about 77 bags, at 6 inch about 115.

Is the kit cheaper than buying each item?

There is no separate kit price. Each item is billed at that day's rate on one GST bill, the same as buying it alone. What the kit saves is a missing item on the day. Cutting and delivery are charged separately; ask for the amount for your site (delivery).

My engineer's bar list gives different steel. Which one do I follow?

The engineer's list. The kit's steel is an estimate scaled from a worked 1000 sq ft roof. Choose "my engineer's bar list" in the kit and send the list on WhatsApp; we weigh out exactly that.

When should the dhalai material reach the site?

In two lots. Sariya, binding wire and cover blocks about a week before, so the steel can be tied and checked. Cement, balu, gitti and WP+200 about two days before, so they can be counted and covered without the cement sitting long on a damp site.

Weather Plus and WP+200 together?

Usually one or the other. Weather Plus is already a water-repellent cement, and UltraTech gives no advice on adding WP+200 to it. With Super or Premium, WP+200 goes in at 200 ml per 50 kg bag (WP+200 per bag).

Where the numbers come from

  1. Our worked roof: how much sariya for a roof slab (40 × 25 ft, 1,314 kg all 10 mm; 1,403 kg with 12 mm main bars; top bars and 10% allowance included).
  2. Bureau of Indian Standards, IS 1786:2008: nominal mass from 0.00785 kg per mm² per metre (10 mm 0.617 kg/m, 12 mm 0.888 kg/m, 8 mm 0.395 kg/m).
  3. Bureau of Indian Standards, IS 456:2000: M20 the lowest grade for RCC (Table 5), 20 mm nominal cover for mild exposure (Table 16). Water at most 25 L per 50 kg bag, the standard figure used across this site.
  4. UltraTech, Weather Pro waterproofing brochure: WP+200 at 200 ml per 50 kg bag, added with the second half of the water.
  5. JSW Neosteel, How much steel is required for a house?: 3.5–5 kg per sq ft of built-up area, a whole-house figure.
  6. Usual practice, labelled where used: 1:1.5:3 with a 1.54 dry factor, 2 spare bags, 1 kg binding wire per quintal, cover blocks on a 2 ft grid, chairs about 1 m apart, a 100 cft trolley.

Send your roof size and dhalai date

We'll send back the kit with today's price, and book the two deliveries for your site.

TASHYABUILDING SOLUTIONS · MUZAFFARPUR
WhatsApp 90310 74624tashyaventures.com