Bathroom fitting checklist: every item for one bathroom, in the order it goes in

The short answer
  1. Pipes and bodies in the wall
  2. Waterproofing
  3. Tiles
  4. WC, basin, taps, geyser

Buy one bathroom in four lots, each on site the day its trade starts. What goes inside the wall and floor comes first, because it can't be added once the tiles are on. The things you see, the WC, basin and taps, come last, so they aren't chipped while the work goes on. Build your list below and send it to us on WhatsApp.

110 / 75
Drain pipes, mm110 for the WC line, 75 for the floor trap line.
2 halves
Bought early, finished lateThe mixer body goes in the wall now; its trim after the tiles.
38
Lines on the listFor a 6 × 8 ft bathroom with a western WC, shower and geyser.
One 6 × 8 ft bathroom, from above
Plan of one bathroom with every item marked by lot A 6 by 8 foot bathroom. Lot 1 items hidden in the wall and floor: the 110 mm WC line and the 75 mm floor-trap line running to the stack outside, the floor trap, the concealed stop cock at the door, the mixer body, cold and hot supply lines and the geyser point. Lot 2: the waterproof coat over the floor and a foot up the walls. Lot 3: floor and wall tiles. Lot 4: the WC, basin, taps, shower and geyser. WC220 or 300 Basin Floor trap110 × 75 Shower,mixer bucket tap Geyserhigh on wall Stop cock Stack Door 110 75 Lot 1 · in the wall and floor Lot 2 · waterproofing Lot 3 · tiles Lot 4 · fixtures cold hot drain, under the floor
Drawn to scale, 1 square = 1 ft. The positions are a common layout, not a rule. The blue band is the waterproof coat carried 1 ft up every wall, as on our bathroom waterproofing page.
Four lots, four trades

Buy in the order the work happens

A bathroom is built by four people one after another: the plumber, the waterproofing man, the tile mason, then the plumber again. Each lot is what one of them needs on his first morning. If it's late, he waits, and so does everyone after him.

1Inside the wall and floor

Before plaster, before the sunk is filled

Drain pipes and the floor trap, the cold and hot supply lines, the concealed stop cock, the mixer body and the geyser point. With an Orissa pan, the pan and its P-trap come now too, because they are bedded into the floor.

If it's late: the mason can't plaster and the sunk can't be filled.

2Waterproofing

Before the filling, and again before the tiles

Used twice: two coats inside the sunk, two more under the tiles. The full method, with its two 48-hour water tests, is on bathroom waterproofing.

If it's skipped: the room below gets the leak, months later.

3Tiles, adhesive, grout

Once the sloped screed is down

Floor and wall tiles from one batch, with a few spare. TileStix for these ceramic tiles, and TileLynk for the joints. Which tile won't slip: bathroom floor tiles.

If short: a second batch rarely matches the first in shade.

4Fixtures, taps, geyser

After tiling and grouting

The WC or cistern, the basin, angle valves, connection pipes, taps, the shower and the geyser. Kept in the carton until the tiles are done, they come out unchipped.

If early: a dropped tile or a mason's hammer cracks the bowl.

This page is the buying list. What to check on site at each stage, before the next trade covers the work, is on the plumbing stage checklist.

The items people get wrong

Some things are decided in lot 1 and bought in lot 4

These are the costly mix-ups. Part of the item, or its exact position, is fixed in the wall or floor long before the part you see arrives. Settle them before the plumber starts, not on the day the WC comes.

Mixer body in the wall and the WC drain in the floor Left: a wall section with the concealed mixer body set into the brick so the finished tile face falls between the min and max marks on its plastic cover; the trim plate and lever go on after the tiles. Right: a floor section with the 110 mm drain pipe rising 220 mm from the finished wall face; the WC sits on it later. MIXER, SIDE VIEW tile face Trim · lot 4 same brandand series Body · lot 1 tile face betweenthe cover's marks coldhot WC DRAIN, SIDE VIEW 220 WC · lot 4 Drainlot 1 slab and sunk filling
Not to scale. 220 mm is the wall-to-drain distance for CERA Chanel 220; Cinco 300 needs 300 mm (CERA). Both are measured from the finished tile face to the middle of the pipe.

Shower mixer

The concealed body goes into the wall in lot 1, set so the finished tile face falls between the min and max marks on its plastic cover (Jaquar's concealed-body sheets). The lever and plate come in lot 4. Buy both halves from the same brand and series, or the trim won't fit the body. Heights to mark: fixture heights.

Western WC

The drain pipe is fixed in lot 1 at 220 or 300 mm from the finished wall. The WC comes in lot 4 and must match it. Choose the model before the drain is laid. How to measure: 220 or 300 mm.

Stop cock

We keep a Jaquar concealed stop cock body (15 mm). Jaquar sells its handle kit separately, so the body is lot 1 and the handle lot 4. One per bathroom shuts the whole room off for a repair.

Make your list

Your bathroom's list, lot by lot

Choose your bathroom and the list fills itself, with quantities worked out from the makers' figures. Untick what you already have, then send it to us on WhatsApp for today's price.

Floor
Toilet

Not sure? Orissa pan or western.

Bathing
Geyser
Wash basin inside
Health faucet
Wall tiles

7 ft is usual practice: how high to tile.

Your list · — lines

Pipe lengths say "by run": your plumber measures them on site, or send us the plan.

Material totalAsk rate
Send — lines on WhatsApp

Prices come back from today's rate. Waterproofing assumes 2 coats in the sunk and 2 under the tiles, a foot up every wall, and the bath wall to 4 ft (bucket) or 7 ft (shower). Tiles and adhesive include 10% for cuts. Cutting and delivery are charged separately; ask for the amount for your site: delivery.

What gets forgotten

Six small items that stop a bathroom for a day

None of these costs much. Each one, missing on the day, sends someone back to the market while the rest of the team waits.

The cleaning door on the drain

Missed: a blockage later means breaking the floor

A bend or tee with a door where the WC line meets the stack. It costs a few rupees more than a plain bend. More on the line: 110 mm SWR pipes.

A trap for the basin

Missed: drain smell through the basin

A western WC has its trap built in, and the 125 × 110 P-trap is only for an Orissa pan. The basin needs a bottle trap under it, and its waste goes past the floor trap into the 75 mm line: two traps in a row slow the drain and make it gurgle. All the traps: traps explained.

Two tins of solvent

Missed: hot joints let go

One for UPVC, one for CPVC, labelled. A UPVC tin used on the hot line is a joint that weeps inside the tiles. Why the hot line is CPVC: CPVC, UPVC, PVC or GI.

Angle valves

Missed: the whole house shut for one tap

One for the basin tap and one for the geyser inlet; beside a western WC a single 2-in-1 valve serves both the cistern and the health faucet. A washer change then shuts one point, not the tank.

Spare tiles from the same batch

Missed: a patch of the wrong shade

The list adds 10%. Keep a few spare from the same batch for repairs later: batch, shade and spares.

On our shelf for one bathroom

The products, and which lot each one is

We sell genuine CERA, Prince and Ashirvad with a GST bill. Taps, mixers, showers, health faucets, angle valves, bottle traps and geysers: we can order them for you; ask on WhatsApp for the time it takes. Today's price for every item: sanitary rates · tile rates · waterproofing rates.

Questions people ask us

Short answers

What do I need to buy for one new bathroom?

Four lots. Lot 1, inside the wall and floor: 110 mm and 75 mm SWR pipe, a floor trap, bends, the stop cock and mixer bodies, UPVC and CPVC supply pipe. Lot 2, waterproofing: a flexible coat, SBR and WP+200. Lot 3: floor and wall tiles, tile adhesive and grout. Lot 4, after the tiles: the WC or cistern, basin, angle valves, connection pipes, taps, shower and geyser. The list builder gives the quantities for your size.

In what order should bathroom materials arrive on site?

Pipes, traps and concealed bodies first, before plaster and before the sunken floor is filled. Waterproofing next, used twice: in the sunk and again under the tiles. Then tiles, adhesive and grout. The WC, basin, taps and geyser come last, after tiling. An Orissa pan is the exception: it is set in the floor before the tiles, so it comes with the first lot.

What size pipe is used for bathroom drainage?

110 mm SWR pipe for the WC line and 75 mm for the floor trap line, both running to the stack or chamber. The basin waste is usually 40 mm and runs past the floor trap into the 75 mm line, as the kitchen sink's does, so there are never two traps in a row. Keep the WC on its own branch; it never shares the floor trap.

Does the wash basin need a P-trap?

It needs a trap, but not the 125 × 110 mm P-trap, which is for an Orissa pan. A wall-hung basin takes a bottle trap under it, and its waste goes past the floor trap into the 75 mm line. A western WC has its trap built in, so it needs none.

When should I buy the shower mixer?

In two halves, but choose it before the plumber starts. The concealed body goes into the wall with lot 1, set so the finished tile face falls between the min and max marks on its plastic cover. The lever and plate are fitted after the tiles. Both halves must be the same brand and series. We order mixers for you, so tell us early.

Do you sell taps, mixers and geysers?

On the shelf we keep CERA sanitaryware, Prince and Ashirvad pipes and fittings, and a Jaquar concealed stop cock body. Taps, mixers, showers, health faucets and geysers we order for you; ask on WhatsApp for the time it takes.

Can I send this list to the shop for a price?

Yes. Make the list in the builder above, untick what you already have, and press Send on WhatsApp. We reply with today's price and what is in stock, and you can collect or take delivery lot by lot. Send photos before the sunk is filled and before the tiles go on, and we will look at them with you.

Arun Tiwari
Thekedar · site work, costs and plumbing, Tashya Ventures

Twenty years on sites around Muzaffarpur. Product sizes and coverage are the makers' own, from the pages listed below. The order of lots and the fitting counts are usual practice on local sites, and the page says so where it uses them.

Where the facts come from

  1. CERA, Chanel 220 (S1013227) and Cinco 300 (S1013199): concealed S-trap at 220 and 300 mm wall distance, seat cover in the pack. Squatting pans: Calina 530 × 425 mm.
  2. Prince, Ultrafit SWR multi floor trap with jali, 110 × 75 mm, as listed by IndustryBuying. Prince's SmartFit Plus and Easyfit pages (via our pipe comparison): UPVC 5–60 °C, CPVC to 82 °C, 24 h before testing a CPVC joint.
  3. Jaquar, ALD-069FT: concealed stop cock body for 15 mm lines, 0.5–5 bar; exposed kit CQT-CHR-23069K sold separately.
  4. V-Guard geyser manuals (Luxecube Avo, Pebble Metallica): multi-function safety valve on the inlet; Pebble Metallica's box holds 2 flexible hoses and the valve.
  5. UltraTech, Weather Pro brochure: Hi-Flex 1 kg per 14–15 sq ft per coat, two coats; WP+200 200 ml per 50 kg bag.
  6. Birla White, TileStix Intero Grip+ (TX2): ceramic up to 450 × 450 mm indoors, 55–60 sq ft per 20 kg at 3 mm. TileLynk brochure: joints 1–6 mm, 1 kg pouch, no coverage figure. Grout estimate: the standard joint formula used by grout makers' calculators (for example UZIN), with 2 mm joints, 8 mm deep.
  7. Birla Pivot catalogue, box contents: 300 × 300 floor 8 tiles = 7.75 sq ft; 300 × 450 wall 6 tiles = 8.72 sq ft.
  8. Waterproofing areas and cement for the screed: the method on our bathroom waterproofing page.

Send us your bathroom

Size, toilet, shower or bucket, geyser or not. We'll send the four lots back with today's price on WhatsApp.