Waterproofing guide · building a house

Waterproofing while you build: the stage-by-stage checklist, from the neev to the last coat before the monsoon

The short answer
  1. Neev
  2. Plinth + DPC
  3. Walls
  4. Lenter
  5. Bathroom
  6. Roof coat
  7. Outside coat

Waterproof while you build, not after the first leak. UltraTech's own plan has two steps: WP+200 in every concrete and plaster job, and a second layer where water hits hardest (roof, bathroom, kitchen, outside walls). Each of the seven stages below can only be done properly while that stage is open. Tick each one before the next begins.

68 L
WP+200, whole house1000 sq ft, one floor: 340 bags of cement at 200 ml each, bought stage by stage.
~228 kg
Hi-Flex, whole houseRoof 162, two bathrooms 60, kitchen washing area 6. Two coats everywhere.
3
Can never be redoneWP+200 in the neev and lenter, and the DPC. Later fixes only work round them.
Seven places, one house
Cross-section of a one-floor house showing the seven places waterproofing goes in while it is built1234567groundfloorbathroomroomfall to khurra →1Neev: WP+200 in the footings2Plinth beam + 40 mm DPC3Walls: WP+200 in outer mortar4Lenter: WP+200, fall, sleeves5Bathroom, kitchen: coat, test6Roof: Hi-Flex × 2 + screed7Outside plaster, then paintWP+200 in the mixCoat (Hi-Flex)DPC
Not to scale: coats, DPC and plaster are drawn many times thicker than they are. WP+200 areas and Hi-Flex: UltraTech Weather Pro brochure. DPC: UltraTech and Dalmia. Bathroom upturn: Birla White.
Now or never

Three kinds of waterproofing job, and when each closes

This is why the order matters more than the brand. Some jobs vanish inside the concrete on the day; some get buried under the next layer; only the last few can wait.

1Only on the day it is cast

WP+200 in the footing, plinth beam, columns and lenter concrete. The DPC. The fall on the slab, the khurras and the pipe sleeves. Miss one and there is no second chance: you cannot add WP+200 to set concrete, and a DPC can't be slid under a finished wall.

2Before the next layer covers it

The sunk coat before the bathroom is filled, the under-tile coat before the tiles, Hi-Flex before the roof screed. Each one is easy on the open surface and means breaking tiles or screed later. Each gets a check before it is covered: a water test, a dry-touch test.

3Can wait for the end

Seep Guard or WallFix 4 on rain-facing walls, waterproof putty inside, exterior paint. These go on last, once the plaster has cured and dried. They protect a wall that is already sound. They cannot make up for jobs 1 and 2.

Weather Plus cement instead of WP+200? UltraTech sells Weather Plus as a water-repellent cement. Use it or WP+200 in a given concrete, not both: UltraTech publishes no advice on mixing the two. The coats in jobs 2 and 3 are needed either way. More: how much WP+200 per bag.

The checklist

Seven stages, what to do, and what to check before moving on

Quantities are for one example house: 1000 sq ft built-up on one floor (25 × 40 ft), RCC frame, outer wall 130 ft round, two bathrooms. Tick as you go; the button at the end sends what is still open to us on WhatsApp.

1

Neev: footings and column necks

Week 1–3 · after digging and PCC
Example house: about 45 bags in footings and necks → 9 L WP+200. Planning figure for 12 footings; your drawing decides.
Before stage 2: footings cured at least 7 days, 10 with PPC or slag cement (IS 456).
2

Plinth beam and DPC

Week 3–5 · the last job below floor level
Example house: plinth beam 200 running ft, 35 bags → 7 L; DPC 5 bags → 1 L. 8 L WP+200.
Before stage 3: walk every wall and look for a gap in the DPC at corners and door lines. Photograph it before the first brick.
3

Walls, columns, lintels and chhajjas

Month 2–3 · brickwork up to lintel and slab
Example house: columns, beams and lintels about 50 bags → 10 L; outer-wall mortar about 38 bags → 7.6 L. 17.6 L WP+200.
Before stage 4: wiring conduit and plumbing routes marked, because the lenter closes them in: wiring before plaster.
4

Lenter (roof slab), dhalai day

Month 3 · cast by the end of April
Example house: 5-inch slab, 96 bags → 19.2 L WP+200, one 20 L can. The full day: waterproofing at chhat dhalai.
Before stage 6: pour a bucket on the cured slab; any puddle after an hour is a low spot to build up before the coat.
5

Bathrooms and kitchen

After the slab, before any floor tiles · fine in the rain
Example house: two 6 × 8 ft bathrooms 56–60 kg Hi-Flex, 6 bags of cement with 1.2 L WP+200, 2 kg SBR; kitchen 5–6 kg. Step by step: bathroom waterproofing.
Before tiles: no damp patch under the bathroom after the 48 h test. Ground-floor bathroom? The test shows as damp on the wall next door instead.
6

Roof: Hi-Flex and screed

About 4 weeks after dhalai · dry days, before mid-June
Example house: 1000 sq ft + 130 ft of parapet strip = about 162 kg, seven 24 kg packs; screed 28 bags → 5.6 L WP+200. Kilos for your roof: how much Hi-Flex.
Before the coat: slab dry to the touch and even in colour. A cast slab that misses the dry spell waits under a tarpaulin until October.
7

Outside plaster, then the last coats

After the rains · paint 28 days after plaster
Example house: about 2,050 sq ft of outside plaster (walls, plinth face, parapet both sides) → 37 bags → 7.4 L WP+200. Paint order: exterior paint for Bihar rain.
Before paint: touch the wall, not the calendar. If it feels cool or looks patchy, wait.

The house is already built and a wall is damp? That is a different job, cause by cause: seelan from foundation to roof. Leaking roof: terrace waterproofing for a finished roof.

When, around the monsoon

Plan the build so the roof is coated before the rain and the outside is painted after it

An example for a house started in February. Muzaffarpur gets most of its year's rain from June to September (CGWB), so two stages are fixed to the calendar: the roof coat before it, the outside paint after it.

Example timeline for a house started in February, showing which waterproofing stage falls before, in and after the monsoonMonsoon, about mid-June to SeptemberFebMarAprMayJunJulAugSepOctNovDecJan1Neev2Plinth, DPC3Walls4Lenter5Bathroom6Roof coat7Outsidedone before the raininside work, fine in the rainworktarai, curingneeds dry dayspaint after 28 days
Example only: your start date moves everything. Rain share: CGWB Muzaffarpur booklet. Waits: see the table.
WaitTime
Concrete curing, OPCIS 456 cl. 13.5.1≥ 7 days
Concrete curing, PPC or slag, or hot weatherIS 456; the slab gets 10–1410–14 days
Slab cast to roof coatCured, then dry: about four weeks~4 weeks
Hi-Flex coat to coatUltraTech, second coat crosswise≥ 8 h
Plumbing under pressureBefore the bathroom coat (usual practice)1 day
Bathroom water test50 mm of water, Birla White48 h
Plaster to exterior primerBirla Opus sheets; dry, not just old28 days
No rain after exterior paintBirla Opus primer sheets4 days
If the lenter slips into May. Don't put Hi-Flex on a damp slab to beat the rain: it blisters and peels. Keep the slab covered, keep the khurras clear, and coat it in the first dry weeks of October. Inside work, bathrooms included, carries on through the monsoon. Rain on dhalai day: casting a slab in the rains.
Your quantities

WP+200 and Hi-Flex for your house, stage by stage

Put in your house. Each stage shows what to buy when that stage starts, so nothing sits on site for months. Planning figures, not a bill of quantities; your engineer's drawing decides the final order.

25 × 40 ft house: 130 ft round. Bathrooms counted as 6 × 8 ft. Plinth beam run taken as 1.54 × the outer wall (inner walls added).

Stage by stage

WP+200, whole house—
Hi-Flex, whole house—
Material totalAsk rate
Send this list on WhatsApp

WP+200: 200 ml per 50 kg bag (UltraTech). Hi-Flex: 1 kg covers 14–15 sq ft for one coat, two coats (UltraTech). Bags: footings 45 per 1000 sq ft (60 for two floors), columns-beams-lintels 50 a floor, outer mortar 0.029 a sq ft of 9-inch wall, slab 77/96/115 per 1000 sq ft, roof screed 28 per 1000, outside plaster 18 per 1000 sq ft (20 mm, 1:4). Prices from today's rate. Cement for the whole house: 1000 sq ft house list.

What goes wrong

Six mistakes made while building that show up as leaks years later

Every one of these is cheap to avoid on the day and dear to fix once the next stage covers it.

yard or road raised laterold ground levelDPCdamp climbs over the DPC

The yard or road raised above the DPC

You see: a damp band at knee height, years after building

UltraTech says to keep the soil below the DPC. In Muzaffarpur lanes are raised and yards filled after every flood, and the DPC ends up underground. Set it high enough now (at least 150 mm above today's ground), and keep fill and outside plaster off it.

!inner wall, no DPC:damp comes up here

DPC only on the outer walls

You see: inner walls damp at the bottom, outer walls dry

Ground water rises under every wall, not only the outside ones. The DPC goes across every wall at plinth level, unbroken at corners and junctions.

water stands, finds the crackkhurra above the water

A flat slab, khurra set high

You see: puddles hours after rain, then a ceiling stain

Standing water finds every hairline crack. The fall (1 in 100 at least) and the khurra level are fixed on dhalai day; building them later means a heavy mortar bed.

hammered through the new slabcracks round the pipe leak for years

No sleeve, hole hammered through later

You see: a damp ring round the pipe on the ceiling

Breaking a new slab cracks it round the pipe, and that ring leaks for years. Tie the sleeves to the shuttering before the pour: pipe sleeves in the slab.

tiles on, no 48 h testfirst leak shows on the ceiling below

Tiled before the water test

You see: the first leak on the ceiling of the room below

Birla White asks for 50 mm of water for 48 hours on the coated floor before anything covers it. After the tiles, a leak means lifting them all.

sun, feet and tank legs wear it thinno screed over the coat

Hi-Flex left without a screed

You see: the coat worn through near the tank and stairs

The coat is under a millimetre thick. Sun, feet, tank legs and sariya dragged for the next floor wear it away. UltraTech recommends a screed or plaster over it every time.

Questions people ask us

Short answers

Should I waterproof during construction or fix it after?

During. WP+200 can only go into concrete on the day it is cast, the DPC only before the walls go up, and the bathroom and roof coats only before tiles and screed cover them. Dr. Fixit puts retrofitting at up to 20 times the cost of building it in, because you also pay to break and remake what sits on top.

Is WP+200 in the concrete enough on its own?

No. It blocks the pores in the concrete, but concrete still cracks as it dries and moves with the sun. That is why UltraTech's plan adds a flexible coat (Hi-Flex) on the roof, bathroom and kitchen. One does not replace the other.

Where does the DPC go, and what is it made of?

At plinth level, on top of the plinth wall or beam, across every wall without a break. Dalmia describes a 40 mm concrete layer no leaner than 1:1.5:3 with gitti up to 12.5 mm; add WP+200 to it. UltraTech puts it about 150 mm above ground and says to keep the soil below it.

How much waterproofing material does a 1000 sq ft house take?

For one floor with two bathrooms: about 68 L of WP+200 over all seven stages and about 228 kg of Hi-Flex (roof 162, bathrooms 60, kitchen 6). Use the stage list above for your size; we send today's price on WhatsApp.

Can the roof coat go on in the monsoon?

No. Hi-Flex needs a cured, dry slab and dry days for both coats. Cast the lenter by the end of April and the roof is coated and screeded by the end of May. If it slips, cover the slab and coat it in October.

Do all outside walls need Seep Guard?

No. Every outside wall gets WP+200 in the plaster and good exterior paint. Seep Guard Vertical or WallFix 4 is an extra layer for the walls that take the rain, put on once the plaster is cured and dry. Neither goes on a damp wall.

Does a ground-floor bathroom need waterproofing?

Yes. There is no ceiling below to stain, so the leak shows as seelan on the wall next door and in the skirting. Coat the floor and 1 ft up the walls as on an upper floor.

Mr Mustafaa
Paint Engineer, Tashya Ventures

Paint and waterproofing at our Reva Road store, Muzaffarpur. Every dose, coat and wait on this page was checked against the makers' sheets on 14 Nov 2026. Quantities match our roof, bathroom and WP+200 pages; where a figure is usual practice, the page says so.

Where the numbers come from

  1. UltraTech, Weather Pro preventive waterproofing brochure: the two steps (integral waterproofing everywhere, double protection for roof, terrace, outside walls, bathroom and kitchen); WP+200 at 200 ml per 50 kg bag in half the water; Hi-Flex 0.6–0.7 mm a coat, two coats at least 8 h apart crosswise, 14–15 sq ft per kg, 12 and 24 kg; screed or plaster recommended over it.
  2. UltraTech, How to prevent dampness in walls: DPC about 150 mm above ground; keep the soil below the DPC.
  3. Dalmia Cement, Steps of construction: DPC 40 mm thick at plinth level, no leaner than 1:1.5:3, aggregate up to 12.5 mm.
  4. Birla White, Seep Guard Seep Blocker 2K warranty booklet: plumbing finished first, gola, water test with 50 mm of water for 48 h; and best bathroom waterproofing method: at least 300 mm up the walls.
  5. Birla White, Seep Guard Vertical brochure: exterior vertical walls, 15 kg.
  6. Birla Opus, AllDry WallFix 4 sheet: exterior waterproof basecoat, not on wet walls; exterior primer sheets: 28-day plaster cure, no rain within 4 days.
  7. Dr. Fixit, roof waterproofing FAQs: slope at least 1:100; FAQs: lighter treatment for kitchens; roof waterproofing for new homes: retrofitting up to 20 times dearer.
  8. Bureau of Indian Standards, IS 456:2000: water-cement ratio 0.5 (25 L per bag); cl. 13.5.1 curing at least 7 days, 10 for blended cement or hot weather.
  9. Central Ground Water Board, Muzaffarpur district booklet: 85% of rain in June–September.
  10. Bag counts per stage: worked the way our cement calculator does it (M20 1:1.5:3, plaster 1:4 at 20 mm, mortar 1:6), for the example house; drip grooves, sill slopes, wall heights and the 1-day pipe test are usual practice.