Lot 1Pump, tank and water
Borewell, pump and a tank go in before the foundation. Every pour needs curing water, and the slab needs 10 to 14 days of it. Which pump: 0.5 HP or 1 HP; tank size: by family.
A house is bought in eight lots, each on site the day its work starts. The list below has every line of all eight, with a quantity for your size. Tick each item as it arrives, print the list, or send it to us for today's rate.
Put in your house. Each line gives a low and a high figure from the same planning figures as our 1000 sq ft cost page and the makers' coverage sheets. Buy to the high figure; your engineer's drawing and plumber's and electrician's layouts decide the final order.
Not sure which structure? RCC frame or brick walls. Plinth in a flood area: how high. Land in katha or dhur: convert to sq ft.
Planning figures, not a bill of quantities. Cement, balu and gitti are split by stage in the same shares as the worked house on our cement and balu and gitti pages. Fittings counts are usual practice. Prices: Ask rate until today's rate is sent. Cutting and delivery are charged separately; ask for the amount for your site (delivery). Every product can be ordered; anything not on our shelf, we order for you, ask on WhatsApp for the time it takes.
Concrete, plaster, tiles and paint each cover what went in before them. A missed sleeve or box found later means breaking something. So these lines sit one lot ahead of where you might expect them.
Borewell, pump and a tank go in before the foundation. Every pour needs curing water, and the slab needs 10 to 14 days of it. Which pump: 0.5 HP or 1 HP; tank size: by family.
The soil is treated while the trench is open and again on top of the plinth filling. Once the floor is down, the only way in is drilling. When and where to treat.
On the list with the lenter, not with the plumbing or wiring. Check them the week before dhalai: pipe sleeves in the slab · dhalai checklist.
Everything inside the wall before plaster, pressure-tested. The mixer's body goes in now; its trim after the tiles. Plumbing by stage · electrical check before plaster.
Two coats in the sunk floor, a 48-hour water test, then two coats under the tiles. Bathroom waterproofing.
WC, basin, taps, switches and fans come after paint, so nothing gets chipped or splashed. Keep the boxes sealed until the day. Bathroom fitting order.
Settle brands and quantities at the start, so the thekedar can't switch a bag halfway. Then let each lot arrive when its work starts.
Fill the list, print it, and give one copy to the thekedar. When someone asks for "a few more bags", the list shows whether the stage is already over its figure.
Send the lot that starts next. Cement kept for months loses strength, and in the monsoon faster; sariya in the open rusts; tiles and sanitaryware get chipped on a busy site.
Not on this list: labour, doors and windows, grills, the borewell boring itself, the naksha fee and the boundary wall. They are separate lines in your budget: what a per-sq-ft figure leaves out.
This page is the list. These pages show how each figure is reached, so you can check a thekedar's number yourself.
Eight lots: water and foundation (pump, tank, anti-termite, cement, sariya, balu, gitti, filling), walls (bricks and mortar), the lenter, pipes and boxes before plaster, plaster and wire, floor with waterproofing and tiles, putty and paint, then the fittings: WC, basin, taps, fans, lights, switches, MCBs and inverter. The list above gives each line with a quantity for your size.
Curing needs water from the first pour of foundation concrete, and the slab needs 10 to 14 days of it. Put in the borewell, pump and a tank before the foundation, not after the house is built.
About 350 to 420 bags when brick walls carry the roof and 400 to 500 bags for an RCC frame, of which about 96 go into a 5-inch roof slab. The list splits the total by stage so each lot arrives fresh. The working: cement for 1000 sq ft.
Fix the brands and the list at the start, but take delivery lot by lot. Cement loses strength in storage, especially in the monsoon, sariya rusts in the open, and tiles and sanitaryware get chipped on a working site.
No. It is the material a building store supplies. Labour, doors, windows, grills, the borewell boring and the naksha fee are separate budget lines, explained on our 1000 sq ft cost page.
Birla White's TileStix Intero Grip+ (TX2) is for ceramic tiles up to 450 × 450 mm indoors. Our 2 × 2 vitrified tiles need TileStix Vitribind, and 2 × 4 tiles, planks and outdoor tiles need Extero. Putty never goes under tiles.
The top slab drops off the list: its cement, gitti, balu and slab sariya. In their place come the sheets and a concrete band on top of the walls, which a brick house in earthquake zone IV needs. Count the sheets with how many roofing sheets.
Arun Tiwari has run house sites around Muzaffarpur and plans material lists with customers at our Reva Road store. The structure lines use the same planning figures as our cost and calculator pages; the finishing lines use the makers' coverage sheets; fittings counts are usual practice. Checked 14 Nov 2026.
Fill it above and press send. We'll reply with today's price for each lot, on WhatsApp. Before dhalai and before plaster, send photos and we'll look at them with you.